Floor finally up and it's nearly filled a 4 yard skip!
20170809_161448.jpg

Base slab primed

20170809_155634.jpg
Got to hit it with a load of leveller! Slab is in good knick with no cracks but really rough in places and the whole floor slopes down from the bay area to the house by 25mm. 20mm thermal boards isn't an option now so will go for 10mm. Went round
after work to set datum dots and my Dad is going to do the rails in sand and cement tomorrow. 4 bays - perimeter and halved with a small bay near the exterior door to level last on my way out.
20170809_195047.jpg

The final finished floor height (even with 10mm boards) will be above the pvc step but I have got a plan to sort that out.
 

macten

TF
Esteemed
Arms
1,871
1,158
Nottingham
Floor levelled and ready for boards and heatbase when ever that will be.

20170811_152258.jpg

20170812_115722.jpg

20170812_152501.jpg

20170812_152529.jpg

20170812_152554.jpg

My Dads first attempt at the rails failed after they started collapsing and blowing away when he opened the door to show me what a neat job he'd done. He thought the mortar mix was predosed and had to just add water and was surprised it wasn't solid after a couple of years in his shed. Told him to go get some new stuff but he's a bit of a womble and forgotten he must have used the cement dose years ago for something else. So his first attempt was basically playing with sand :D
 

macten

TF
Esteemed
Arms
1,871
1,158
Nottingham
Great job on the levelling, how did he make the barriers just a trowel?

Just dump some sand/cement between the dots and press down with a wet straight edge, cut excess off sides and slide off. I learnt this technique off Phil Hobson on this forum. Best thing about it is you know it will be perfect and doing it in bays means you can take on any bad floor any size on your own. Even better than that is you're not rushing and stressing when you're doing it.
 
Last edited:

macten

TF
Esteemed
Arms
1,871
1,158
Nottingham
Had today free to finally get back to my mum and dads with the hope of tiling at some point next week.
Fitted the insulation boards and heat base mat.

IMG_0070.JPG

IMG_0071.JPG

IMG_0080.JPG

IMG_0081.JPG

IMG_0082.JPG

Hopefully my sparky mate will be free to help me tomorrow so I can get the cable laid and SLC.
My Dad, being my Dad, doesn't want surface mounted cables like they did when he had the alarm fitted (I'm sure that install is illegal as the wire looks far too thin for the ring main) and he doesn't want the hassle of the other side of the wall chased - fair enough it's wall papered. Think the only way he'll be happy is if we have the spur, thermostat and fan/light switch in a row. So drilled a brick out in the hope that my sparky will be able to feed the cables through the cavity, do his thing and make it all work.

IMG_0083.JPG
 

macten

TF
Esteemed
Arms
1,871
1,158
Nottingham
Was really easy to use Jake and so much less faffing than cutting mesh and turning bits of mat. Suppose the only worry I had was 'what if there's too much cable? I'd be screwed' but I sent you a plan and you said 165m would be fine and it was. My sparky fits a lot of eUFH but he'd not seen this kit before and he was well impressed. I've passed on Uheats details to him. Do I need the final invoice for the warranty Jake? I've only got the delivery receipt and a revised quote.

Went round today to set out and familiarise myself with the tiles and pattern they wanted and I ended up dry laying the lot.
So just need a couple of days free to stick'em and grout.

IMG_E0117.JPG

IMG_E0118.JPG

IMG_E0119.JPG

IMG_E0120.JPG
 

Uheat - Jake

TF
TF Official Sponsor
143
743
Was really easy to use Jake and so much less faffing than cutting mesh and turning bits of mat. Suppose the only worry I had was 'what if there's too much cable? I'd be screwed' but I sent you a plan and you said 165m would be fine and it was. My sparky fits a lot of eUFH but he'd not seen this kit before and he was well impressed. I've passed on Uheats details to him. Do I need the final invoice for the warranty Jake? I've only got the delivery receipt and a revised quote.

Good to hear, as long as I have the warranty cards returned that'll be fine.
 

Lou

Admin
Staff member
888
1,473
Staffordshire

Reply to Would you bother with 2 mats? in the Tiling on Underfloor Heating area at TilersForums.com

Subscribe to Tilers Forums

There are similar tiling threads here

    • Like
Hello, this is my first post here, but I have been doing some reading. I am going to be tiling...
Replies
7
Views
425
Hi guys, had some great advice here before so thought I would ask here for advice again...
Replies
0
Views
379
    • Like
Hi everyone, With a kitchen renovation, Mrs choose the white mirror quartz floor tiles from a...
Replies
4
Views
1K
    • Like
Hi everyone I am building my own house and now I'm ready to tile the floor downstairs. I have...
Replies
1
Views
1K
Hi! I'm looking for some advice, I have laid some SLC (Mapei 1210) in our conservatory in...
Replies
5
Views
2K

Underfloor Heating Trending Threads

Advertisement

Thread starter

macten

Esteemed
Arms
TF
Joined
Location
Nottingham

Thread Information

Title
Would you bother with 2 mats?
Prefix
Forum
Tiling on Underfloor Heating
Start date
Last reply date
Replies
59

Thread Tags

Tags
would

Which tile adhesive brand did you use most this year?

  • Palace

    Votes: 9 6.1%
  • Kerakoll

    Votes: 14 9.5%
  • Ardex

    Votes: 11 7.4%
  • Mapei

    Votes: 44 29.7%
  • Ultra Tile

    Votes: 17 11.5%
  • BAL

    Votes: 35 23.6%
  • Wedi

    Votes: 3 2.0%
  • Benfer

    Votes: 2 1.4%
  • Tilemaster

    Votes: 21 14.2%
  • Weber

    Votes: 18 12.2%
  • Other (any other brand not listed)

    Votes: 15 10.1%
  • Nicobond

    Votes: 7 4.7%
  • Norcros

    Votes: 3 2.0%
  • Kelmore

    Votes: 4 2.7%
Top