prceramics
Priced a job up the guy rang me and said he wants 62 m2 of travertine laid on his floor popped over to have a look concrete floor, he had a sample told him i could do it for £30 per m2 witch came to £1800 including grout addy and sealer floor to be primed and every tile back buttered he said would you do it for £1750 i say sure! so i started to measure the room and it was only 50m2 being honest i call him over and say mate its only 50m2 it will be cheaper he said no not just that room the adjoining room and hallway i measured it up and it came to 93m2 he said oh i thought it was 63m2 so i told him i will have to reprice it which his reply was i am not paying anymore than agreed my final offer was £27 perm2 plus i would of had to work right the way through the weekend with another tiler helping was £2500 his reply was he has had a quote at 19 per m2 elsewhere and would go with that do you think he was trying to pull a fast one ?