Hi,
I hope you can help?
I have a fully dry screed that the Plasterer laid like a ploughed field. I have used a floor grinder to flatten, I have vacummed and primed with 1 coat of SBR today diluted 4 parts water 1 part BAL sbr (as recommended by BAL for dust suppression)
I forgot to ask technical if I needed to apply 2 coats, have checked all literature and cannot find anything mentioning second coat. Please could you answer?
For information this is the plan:
Best regards,
Richard.
I hope you can help?
I have a fully dry screed that the Plasterer laid like a ploughed field. I have used a floor grinder to flatten, I have vacummed and primed with 1 coat of SBR today diluted 4 parts water 1 part BAL sbr (as recommended by BAL for dust suppression)
I forgot to ask technical if I needed to apply 2 coats, have checked all literature and cannot find anything mentioning second coat. Please could you answer?
For information this is the plan:
- Screed dry (over 4 months)
- 1 coat sbr applied today
- Marmox over that using BAL ptb
- lay UFH
- Mapei renovation screed
- tile with porcelain
Best regards,