It certinly does so I stand corrected
1. Prime all surfaces with BAL PRIME APD and allow to dry
(15-30 mins).
2. Using a suitable brush or steel float, apply
BAL WATERPROOF COATING at:
– Internal and external corners of walls/partitions
– Wall junctions with bases/upstands/columns
– At pipe penetration points/drainage channels/outlets
– Junctions of different bases/background materials
– Cracks and joints in background/base
3. Reinforce with BAL POLYESTER TAPE.
4. Apply second coat of BAL WATERPROOF COATING over
the BAL POLYESTER TAPE.
5. Using brush or steel float, apply BAL WATERPROOF
COATING to primed walls at a max. 2mm thickness.
6. Apply BAL WATERPROOF COATING to primed floor.
7. Reinforce with BAL POLYESTER MATTING (may be cut
to correct size with scissors).
If applying in heavy duty wet areas (e.g. communal showers
and industrial wet process areas) and/or where some vibration
or deflection in the base may be expected (e.g. timber bases):
8. Bed matting into coating and apply a second layer of
BAL WATERPROOF COATING over top.
9. Allow membrane to dry for min. 24 hours before tiling.
When dry, background is suitable for BAL ready-mixed (walls
only) or cementitious powder adhesives. No priming required.
NOTE: BAL WATERPROOF COATING does not provide a wearing
surface and is designed for use with tiling.