Hi everyone, new to the site but have been tiling for around 14 years, in that time i have had zero issues until now😔. Just looking for some advice from the other members.
I completed a porcelain floor installation back in november 2020, over wet ufh, i was told the screed had been down months, i always carry a moisture meter so a week prior to tiling i took some readings, they were showing 12 to 14 % moisture, the follwung week when arrived at agreed date i took more readings that came back 7 to 8%, i double primed floor, laid mapetex matt with mapei adhesive, i then proceeded to tile, after 7 days the floor was complete and solid, fully bedded with no issues, due to bifold doors being delayed i was then booked to re-visit in February to finish off the cuts, upon arrival i was told by the client that the tiles were popping, i was totally shocked and decided to lift a tile, i found small pools of water sitting amongst the adhesive, the adhesive was also yellow and had not set and the matt was damp, it seems obvious that the screed wasn't dry enough and now im faced with legal action, the screeder left no approx drying time to client, and the plumber doesn't answer my calls, i know that a moisture meter doesn't accurately read drying screeds but does a tiler now have to carry hygrometer with them? I haven't slept due to the stress, is this really my fault? Any advice positive or negative would be appreciated.
Thanks
Dan
I completed a porcelain floor installation back in november 2020, over wet ufh, i was told the screed had been down months, i always carry a moisture meter so a week prior to tiling i took some readings, they were showing 12 to 14 % moisture, the follwung week when arrived at agreed date i took more readings that came back 7 to 8%, i double primed floor, laid mapetex matt with mapei adhesive, i then proceeded to tile, after 7 days the floor was complete and solid, fully bedded with no issues, due to bifold doors being delayed i was then booked to re-visit in February to finish off the cuts, upon arrival i was told by the client that the tiles were popping, i was totally shocked and decided to lift a tile, i found small pools of water sitting amongst the adhesive, the adhesive was also yellow and had not set and the matt was damp, it seems obvious that the screed wasn't dry enough and now im faced with legal action, the screeder left no approx drying time to client, and the plumber doesn't answer my calls, i know that a moisture meter doesn't accurately read drying screeds but does a tiler now have to carry hygrometer with them? I haven't slept due to the stress, is this really my fault? Any advice positive or negative would be appreciated.
Thanks
Dan