Cabnero
Hi guys. Due to tile my mum's bathroom next week but the guy doing the plumbing I asked to lay the ply and nog the floor as I'm only in and out and he need to do his pipework etc. I've asked him to prime underneath etc.however I was there today after he left and having checked I'm not 100% about what he's done. Firstly he's laid the ply in 4 squares so 4 corners are almosthe meeting but slightly staggered. Im not sure I would have done this as feel it could be a weak point?. Also he has nogged the floor. The perimiter is all done and is fine but the noggins are about 800mm apart. I was going to ask him to put more noggins in to make 400 centers. Would this be correct or am I being ott. The noggins are 6x2 I think. The joist are 8x2 and the tiles will be be 600x600 porcelain. Hardi and ditra are both being laid. While the ply is not screwed down I would appreciate your advice. Thanks.