S
Sachin Parab
Dear All,
I have recently has procelain tiles laid in my downstairs area which is around 80sq.m. We have UFH (water based) installed as well.
The builder has was Lafarge (anhydrite) screed. He has allowed enough curing time (3 weeks) and heating was commissioned in the right way (starting lower first and gradually increasing and then turning down 48 hours before tiling commenced). Following the tiling we started noticing movement in the tiles and following further investigation by the builder it was found that a primer was not used. to bond the adhesive.
The builder has then removed all the tiles. Floor was then checked with hygrometer for mositure which had all the right readings. Floor was then sanded and primed with 2 coats (1st coat 1:5 left for 12 hours and 2nd coat 1:1 left for 12 hours). UFH was turned off 48 hours before priming the floors. Tiles were laid and UFH left off for 3 weeks and now turned on gradually. The adhesive used was Mapei flexible keraquick adhesive and mapei flexible grout.
A few days before the UFH came on I noticed one area of grout coming out. Since the UFH has come on the grout has started to come out in a few tiles and about 4 tiles are showing movements at the edges.
The builder has raised a complaint with CEMEX and an investigation has been initiated.
I will be grateful if I could get any advise on any steps have been missed and if anything else can be done.
The fortunate thing the builder has accepted accountability and has assured he will get it sorted whatever needs be, but the problem I have is that all my work has been completed and all furniture in place now, but I guess I will have to deal with it.
Thanks in advance
Sachin
I have recently has procelain tiles laid in my downstairs area which is around 80sq.m. We have UFH (water based) installed as well.
The builder has was Lafarge (anhydrite) screed. He has allowed enough curing time (3 weeks) and heating was commissioned in the right way (starting lower first and gradually increasing and then turning down 48 hours before tiling commenced). Following the tiling we started noticing movement in the tiles and following further investigation by the builder it was found that a primer was not used. to bond the adhesive.
The builder has then removed all the tiles. Floor was then checked with hygrometer for mositure which had all the right readings. Floor was then sanded and primed with 2 coats (1st coat 1:5 left for 12 hours and 2nd coat 1:1 left for 12 hours). UFH was turned off 48 hours before priming the floors. Tiles were laid and UFH left off for 3 weeks and now turned on gradually. The adhesive used was Mapei flexible keraquick adhesive and mapei flexible grout.
A few days before the UFH came on I noticed one area of grout coming out. Since the UFH has come on the grout has started to come out in a few tiles and about 4 tiles are showing movements at the edges.
The builder has raised a complaint with CEMEX and an investigation has been initiated.
I will be grateful if I could get any advise on any steps have been missed and if anything else can be done.
The fortunate thing the builder has accepted accountability and has assured he will get it sorted whatever needs be, but the problem I have is that all my work has been completed and all furniture in place now, but I guess I will have to deal with it.
Thanks in advance
Sachin