U
Unregistered
We currently have concrete laid, which was done back in October, with under-floor heating within (wet system) We are hoping to start laying Limestone Tiles...20mm thick on 25 Mar, but the plumber is yet to get the heating commissioned. The forecast date for this is early next week, leaving just 1 week to heat the concrete and bring it up to temperature. We have around 4" of concrete to heat with the heating, and were inetrested if there was a good way to tile from 25 Mar, but which recognises that we only have 1 week from heating on to start tiling. Our tiler suggests at least 2 weeks to bring the heating up to temp, before we start tiling, so that we don't stress the concrete and get cracks.
What can we do?
What can we do?