Done 70 mtrs of 60x60 porcelain on dittra over a water underfloor heating system. I finished a couple of weeks ago but as the customer hasnt moved in yet the heating hasnt been turned on.
I was wondering what the rules are on turning the heating back on. It was on for a few weeks before tiling but was turned off atleast a week before laying the dittra.
Ive read on here one or two different times for waiting.
There is a control in every room and can be set to a temp, im sure it wont need to be turned on for a while yet but i take it it has to be turned on gradually upto their prefered heat.
Any info is always appreciated.
Thanks
Mark
Done 70 mtrs of 60x60 porcelain on dittra over a water underfloor heating system. I finished a couple of weeks ago but as the customer hasnt moved in yet the heating hasnt been turned on.
I was wondering what the rules are on turning the heating back on. It was on for a few weeks before tiling but was turned off atleast a week before laying the dittra.
Ive read on here one or two different times for waiting.
There is a control in every room and can be set to a temp, im sure it wont need to be turned on for a while yet but i take it it has to be turned on gradually upto their prefered heat.
Any info is always appreciated.
Thanks
Mark