I did a quote last week for laying marble floor tiles. Please see quote below:
Please find (below), an estimate of the costs involved in providing tiling services (as previously discussed).
You will have to purchase a total amount of 160 tiles, as the amount you have ordered will not cover the area you want tiled. Also, you will have to purchase another bag of adhesive, and a bottle of primer. Any unused adhesive or full tiles can be returned to Topps Tiles for a full refund.
Natural stone (as explained to you) needs to be treated very carefully. The process of laying the tiles is very time consuming. Each tile has to be ‘back buttered’ (i.e. a layer of adhesive is applied to the back of the tile). The tile is then placed onto the cement adhesive (which has already been applied to the floor). The cutting of each tile has to be done using a wet cutter, the tile has to be then dried.
I have allowed 4 days labour for the job.
All work to be carried out by myself (Sean Kelly), using the latest tiling techniques and to the standards I would wish & demand to have in my own home.
If you wish to instruct my services then please do not hesitate in contacting me on one of the numbers above.
After a few days I sent the customer a polite email:
Dear Hameed,
I just wondered what you thought of my quote (and the advice I gave you last week).
Basically, I am after some feedback on what I can do different in my quoting system.
Many thanks.
Sean
A few minutes ago I got a reply:
I found Your Quote was too Excessive Price, i have get it done by GBP 220.Two days work.
i hope you make reasonable price in your Quotes in the future to customers so they can afford to call you.
Kind Regards
Hameed
So, the question is am I expensive? (I am based just inside the M25). The kitchen was a bare room and it needed leveling in places.
Cheers
Sean
Dear Hameed,
You will have to purchase a total amount of 160 tiles, as the amount you have ordered will not cover the area you want tiled. Also, you will have to purchase another bag of adhesive, and a bottle of primer. Any unused adhesive or full tiles can be returned to Topps Tiles for a full refund.
Natural stone (as explained to you) needs to be treated very carefully. The process of laying the tiles is very time consuming. Each tile has to be ‘back buttered’ (i.e. a layer of adhesive is applied to the back of the tile). The tile is then placed onto the cement adhesive (which has already been applied to the floor). The cutting of each tile has to be done using a wet cutter, the tile has to be then dried.
I have allowed 4 days labour for the job.
All work to be carried out by myself (Sean Kelly), using the latest tiling techniques and to the standards I would wish & demand to have in my own home.
If you wish to instruct my services then please do not hesitate in contacting me on one of the numbers above.
Description
Qty.
Unit Price
Line Total
VAT Rate
VAT Amount
1
£640.00
£640.00
0%
£0.00
After a few days I sent the customer a polite email:
Dear Hameed,
I just wondered what you thought of my quote (and the advice I gave you last week).
Basically, I am after some feedback on what I can do different in my quoting system.
Many thanks.
Sean
A few minutes ago I got a reply:
I found Your Quote was too Excessive Price, i have get it done by GBP 220.Two days work.
i hope you make reasonable price in your Quotes in the future to customers so they can afford to call you.
Kind Regards
Hameed
So, the question is am I expensive? (I am based just inside the M25). The kitchen was a bare room and it needed leveling in places.
Cheers