How long to wait until tiling onto 75mm screed

Tilers Forums Official Sponsors

If I remember rightly Schluter claim it can be tiled as soon as weight bearing . I stand to be corrected and if I was doing this I would obviously check .


The phrase they like to use is,
'as soon as its mechanically repairable'
Tape the joints for moisture sensitive stone, otherwise not necessary, but certainly doesn't hurt, personally I'd prefer it.
But yes as soon as its load bearing.

To fast track a screed a 'vapour equalisation barrier' must be used i.e.
Ditra 25
Durabase mat

These mats are not for wet ufh obviously, but they still do the same job as above.
Ditra E Heat mat
Variopro ufh mat.
 
i treat S&C screed beds over UFH the same way as concrete 1 week per inch to dry, so at 75mm i would leave at least three weeks and not force dry it by using the UFH. I prefer to let it dry naturally. Then go with Ditra or durabase for crack suppression.
 
You can tile on a green screed after 28 days using tilemaster ultimate but that doesn't offer any uncoupling if you want that.
 
Is green screed flexible enough for the ufh..?

Maybe not on a green screed.

IMG_0376.PNG

IMG_0378.PNG
 
you could probably used ultimate to stick crack mat down then tile with ultimate on top of that. Cheaper than ditra
 

Advertisement

Thread Information

Title
How long to wait until tiling onto 75mm screed
Prefix
N/A
Forum
Canada Tile Advice
Start date
Last reply date
Replies
40

Advertisement

UK Tiling Forum

Thread statistics

Created
ashurst,
Last reply from
Geoff Thacker,
Replies
40
Views
35,966

Thread statistics

Created
ashurst,
Last reply from
Geoff Thacker,
Replies
40
Views
35,966
Back