i started a bathroom the begining of last week for a plumber i do some work for all the materials are being supplied by his client and were all on site apart from the trims (there some kind if fancy brush steel the client sourced).
i was told they would be with me that day or they following morning, by the end of the week they still havnt turned up, i have other work booked in which will tie me up for a week and a half to two weeks, its work i cant but back as im tied in with plumbers and kitchen fitters and it will throw there schedules out the window.
the plumber/client ain't happy and expect me to drop everything when the trims arrive and finish there job (about 2 days work with the grouting).
ive told them when ive finished my other comitments and the trims are in i'll be back to finnish off.
got a feeling its going to get messy with them finishing the job and not paying me for the 4 days ive worked.
where would you think i stand from a legal piont of veiw should the worst happen.
i was told they would be with me that day or they following morning, by the end of the week they still havnt turned up, i have other work booked in which will tie me up for a week and a half to two weeks, its work i cant but back as im tied in with plumbers and kitchen fitters and it will throw there schedules out the window.
the plumber/client ain't happy and expect me to drop everything when the trims arrive and finish there job (about 2 days work with the grouting).
ive told them when ive finished my other comitments and the trims are in i'll be back to finnish off.
got a feeling its going to get messy with them finishing the job and not paying me for the 4 days ive worked.
where would you think i stand from a legal piont of veiw should the worst happen.
Last edited: