S
Stu2010
Hi
I find myself in some trouble... Stripped off a load of old tiles around the old shower area.. Then put a 5mm coat of Thistle bonding and then a skim coat to finish.
I'm using Ceramic tiles.. tiles are about 7mm thick
I've just spoken to Thistle technical support and they have said i need to wait 5 - 6 weeks to let the bonding an plaster dry before tiling...
1) HELP --Do i really have to wait 6 weeks before tanking with BAL WP1 and tiling?...
2) could i do it in a week?
3) If i did it in a week... what could go wrong??
please help!!
thanks
Stu
I find myself in some trouble... Stripped off a load of old tiles around the old shower area.. Then put a 5mm coat of Thistle bonding and then a skim coat to finish.
I'm using Ceramic tiles.. tiles are about 7mm thick
I've just spoken to Thistle technical support and they have said i need to wait 5 - 6 weeks to let the bonding an plaster dry before tiling...
1) HELP --Do i really have to wait 6 weeks before tanking with BAL WP1 and tiling?...
2) could i do it in a week?
3) If i did it in a week... what could go wrong??
please help!!
thanks
Stu
Last edited by a moderator: