Gazzer
Ok so, I tile a bathroom. At the end of the bath is a gap approx 500mm between bath and wall. 100mm up the make a raised floor so to cover the waste pipe. The floor is tiled too, and I carry the floor tiles just under the bath so as bath panel sits on the floor tile. Same with this boxing where there will be an end panel. Job is done and all paid, clients happy bunnies !
Today a phone call saying that I have pulled the floor tiles which sit on the raised panel under the bath too far and they cant get the panel on. Now I cut these tiles to the raised floor but surely....unless I am wrong .....the panel should be cut around this raised section so as the panel sits tight against the tile and not the tile against the panel ??
Does this make sense and am I wrong ???
Today a phone call saying that I have pulled the floor tiles which sit on the raised panel under the bath too far and they cant get the panel on. Now I cut these tiles to the raised floor but surely....unless I am wrong .....the panel should be cut around this raised section so as the panel sits tight against the tile and not the tile against the panel ??
Does this make sense and am I wrong ???