Hi all,
Im after some advice on concrete floors and drying times. I have a wet room to tile in Travertine with electric UFH and the customer only wants the finished floor to be the same height as the floor leading into the wetroom. This has caused some problems as the floor is concrete in a bungalow. The plumber has dug the floor down so we can build it up to the correct height and has gone down about 3 inch which has hit some polystyrene insulation which is also 3 inch thick, its then concrete again. So basically we have a 3 inch ploystyrene floor at the moment which only needs to be raised about 2 inch to allow for UFH, DITRA, TILES etc.
My questions are
1. Is the required min depth of concrete 3 inch? Thats what we are thinking.
2. Is it ok to tile on concrete over insulation or is this a floating floor?
3. Would it be ok to reduce the insulation to 2 inch (new insulauion) and then build up with 3 inch of concrete?
4. If so how long will it take to dry so i can tile? I understand its 1 day per mm of thickness to dry which is about 75days???
5. Is there anyway of being able to start tiling sooner than *** days as we want to get cracking?
Sorry for all the questions, just so you know my original plan before this was to lay insulation boards, then wires ontop, slc on the wires, de coupling on slc (once dry) then tile.
6. Will i be able to start tiling as soon as i can walk on concrete because of the de coupling/Ditra?
Any advice would be great
Cheers
Im after some advice on concrete floors and drying times. I have a wet room to tile in Travertine with electric UFH and the customer only wants the finished floor to be the same height as the floor leading into the wetroom. This has caused some problems as the floor is concrete in a bungalow. The plumber has dug the floor down so we can build it up to the correct height and has gone down about 3 inch which has hit some polystyrene insulation which is also 3 inch thick, its then concrete again. So basically we have a 3 inch ploystyrene floor at the moment which only needs to be raised about 2 inch to allow for UFH, DITRA, TILES etc.
My questions are
1. Is the required min depth of concrete 3 inch? Thats what we are thinking.
2. Is it ok to tile on concrete over insulation or is this a floating floor?
3. Would it be ok to reduce the insulation to 2 inch (new insulauion) and then build up with 3 inch of concrete?
4. If so how long will it take to dry so i can tile? I understand its 1 day per mm of thickness to dry which is about 75days???
5. Is there anyway of being able to start tiling sooner than *** days as we want to get cracking?
Sorry for all the questions, just so you know my original plan before this was to lay insulation boards, then wires ontop, slc on the wires, de coupling on slc (once dry) then tile.
6. Will i be able to start tiling as soon as i can walk on concrete because of the de coupling/Ditra?
Any advice would be great
Cheers