Leave 7 days after laying.
Commission ufh and put on low for as long as it takes to dry.
Sand floor to remove latience a few days after heating is turned on ( will set like rock if left any longer) this also helps drying times, a the polymers act like a plastic , trapping moisture.

When it's dry, turn off heating and tile.
 
J

J Sid

Leave 7 days after laying.
Commission ufh and put on low for as long as it takes to dry.
Sand floor to remove latience a few days after heating is turned on ( will set like rock if left any longer) this also helps drying times, a the polymers act like a plastic , trapping moisture.

When it's dry, turn off heating and tile.
sand and cement?
 
S

Spacey

very deep for gypsum based. optimum for those is around 45mm i believe

Yeah doesn't mean it couldn't be though.
It's the most commonly used screed these days over UFH And builders as we know don't always follow the rules.
Could just be a fibre reinforced screed but Id want to be sure what I'm dealing with before laying anything.

In answer to the original question With UFH commissioned and running It's possible to dry it out in about two weeks
 
D

Dumbo

Yeah doesn't mean it couldn't be though.
It's the most commonly used screed these days over UFH And builders as we know don't always follow the rules.
Could just be a fibre reinforced screed but Id want to be sure what I'm dealing with before laying anything.

In answer to the original question With UFH commissioned and running It's possible to dry it out in about two weeks
You shouldn't force dry s&c screed
 

Sean Kelly

TF
Arms
647
1,068
Ruislip
If time is an issue and cost is not an issue then use Ardex A38 (Ultra Rapid Drying Cement for Internal & External Screeds).

Screed the floor and tile after 4 hours. I believe it works out at 1.5 times more than the cost of normal screed.

I have not used this product myself, I got the info from asking the Ardex reps at a trade day.
 

Reply to How long to wait until tiling onto 75mm screed in the Canada Tile Advice area at TilersForums.com

Subscribe to Tilers Forums

There are similar tiling threads here

Hi all I’m so glad to have stumbled upon this forum, which seems to be a treasure trove of...
Replies
5
Views
3K
gamer1
G
    • Like
Hi everyone I am building my own house and now I'm ready to tile the floor downstairs. I have...
Replies
1
Views
1K
We had a water underfloor heating installed and tiled over. 3 months later we noticed many tiles...
Replies
7
Views
3K
Amethsyt
A
Just seen Rocatex on uHeat.co.uk and thought hmmm that's a new one on me. Anybody used it yet...
Replies
3
Views
1K
I am sure someone will know a good practice solution. We started a wetroom last year and then...
Replies
1
Views
3K

Advertisement

Thread Information

Title
How long to wait until tiling onto 75mm screed
Prefix
N/A
Forum
Canada Tile Advice
Start date
Last reply date
Replies
40

Which tile adhesive brand did you use most this year?

  • Palace

    Votes: 5 4.5%
  • Kerakoll

    Votes: 8 7.2%
  • Ardex

    Votes: 7 6.3%
  • Mapei

    Votes: 32 28.8%
  • Ultra Tile

    Votes: 14 12.6%
  • BAL

    Votes: 28 25.2%
  • Wedi

    Votes: 3 2.7%
  • Benfer

    Votes: 2 1.8%
  • Tilemaster

    Votes: 19 17.1%
  • Weber

    Votes: 18 16.2%
  • Other (any other brand not listed)

    Votes: 13 11.7%
  • Nicobond

    Votes: 5 4.5%
  • Norcros

    Votes: 3 2.7%
  • Kelmore

    Votes: 2 1.8%
Top