How long to wait until tiling onto 75mm screed

Tilers Forums Official Sponsors

A

ashurst

I am having wet underfloor heating installed on top of 150mm insulation. The screen will be approximately 75mm. I will be laying 10mm porcelain tiles. How long should I realistically wait until tiling onto the area as I am reading conflicting things.

I am hoping that 21 days should surfice
 
Leave 7 days after laying.
Commission ufh and put on low for as long as it takes to dry.
Sand floor to remove latience a few days after heating is turned on ( will set like rock if left any longer) this also helps drying times, a the polymers act like a plastic , trapping moisture.

When it's dry, turn off heating and tile.
 
Leave 7 days after laying.
Commission ufh and put on low for as long as it takes to dry.
Sand floor to remove latience a few days after heating is turned on ( will set like rock if left any longer) this also helps drying times, a the polymers act like a plastic , trapping moisture.

When it's dry, turn off heating and tile.
sand and cement?
 
very deep for gypsum based. optimum for those is around 45mm i believe

Yeah doesn't mean it couldn't be though.
It's the most commonly used screed these days over UFH And builders as we know don't always follow the rules.
Could just be a fibre reinforced screed but Id want to be sure what I'm dealing with before laying anything.

In answer to the original question With UFH commissioned and running It's possible to dry it out in about two weeks
 

Advertisement

Thread Information

Title
How long to wait until tiling onto 75mm screed
Prefix
N/A
Forum
Canada Tile Advice
Start date
Last reply date
Replies
40

Advertisement

UK Tiling Forum

Thread statistics

Created
ashurst,
Last reply from
Geoff Thacker,
Replies
40
Views
35,968

Thread statistics

Created
ashurst,
Last reply from
Geoff Thacker,
Replies
40
Views
35,968
Back