we have just taken over a job, where the tiler before had got it so wrong,
1 fixed to 6mm ply
2 did not seal floor
3 spot fixed floor and walls
4 600x400 tiles onto plaster , spot fixed
5 all floors are heated no ditra matting
6 grey adhesive on travertine
7 no flexible grout
8 butted together using sandpaper as joints which gave 0.5 joint
9 did not seal floors
And this guy says he has been tiling for 50 years , well its unbeleavable and they let him carry on for 8 plots, plumbers where telling me it was easy to repair the tiles as they could pull them off with there hands , so far they have striped 2 plots around 120m2 per unit , and do it in 3 days that must be a record and saved around 140m2 so far,
They had a meeting and asked him why , he said its the way he has tiled all the time , when they said its not what its recommend by adhesive and grout companys and bsi he said what do they know they only make the stuff , amazing
1 fixed to 6mm ply
2 did not seal floor
3 spot fixed floor and walls
4 600x400 tiles onto plaster , spot fixed
5 all floors are heated no ditra matting
6 grey adhesive on travertine
7 no flexible grout
8 butted together using sandpaper as joints which gave 0.5 joint
9 did not seal floors
And this guy says he has been tiling for 50 years , well its unbeleavable and they let him carry on for 8 plots, plumbers where telling me it was easy to repair the tiles as they could pull them off with there hands , so far they have striped 2 plots around 120m2 per unit , and do it in 3 days that must be a record and saved around 140m2 so far,