V
Verona
Hi mates!
This is the first time I have been this annoyed with tradesmen...
A plumber we have been doing works for in the past had two jobs we quoted for a long while ago. The one job was finally ready to start 29th but got a text very late (11pm) Sunday night (only after chasing him since Friday 26th) saying the job wasn't ready until Thursday!
Needless to say it was too late to arrange another job for start Monday morning, so emailed another customer saying that the job we had booked in later the week could start already Tuesday. So far so good, other than this customer wasn't ready and then went ahead to book another tiler! So two jobs down... as in lost!
The plumber's job supposing to start 2nd July was again delayed one day, to start Friday 3rd! Again late night Thursday a text informed that the job wouldn't be ready until Saturday AFTERNOON! Who are to start a job at that time may I ask? :incazzato:
Well, started the job Monday morning 6th July - one week delayed without other jobs booked in the time wasted due to poor information from this plumber guy!
The kitchen splashback and floor was suppose to take 2-2.5 days max. It developed into taking a FULL week, finishing grouting Saturday mid day!!! :yikes: It turned out that when starting on tiling the splashback the worktop not entirely installed, so this would only be finish 5 days later on Saturday.
All of a sudden the hallway was to be tiled as well (not a problem as underfloor heating in kitchen wasn't installed as promised). Was told late Tuesday when requesting an update that this would be done Wednesday, so leaving us with another wasted day without enough notice given to take on another job. :juggle2:
The underfloor heating was then suppose to be in place to start tiling in the morning of Thursday - went on site only to find the house locked and the plumber not arriving until 9.30 starting to lay the underfloor heating!!!
Assisted laying the UFH as nothing else to do. Started tiling at noon! Went back Friday to finish floor and grout the hallway. Only to having to return Saturday to finish the splashback as worktop then installed.
Original quote accepted was £320. Was told by the plumber to charge extra as the 3 sq meter hallway wasn't included in quote. Did so and added a bit extra for assisting laying the underfloor heating, in total £120 extra (with a reminder to the plumber that the job had been delayed a week and taken twice the time).
Now I have just received this email from him saying:
"Extra costs of £130 i find to be a little excessive for the extra few hours
that the job went over. I am willing to pay extra £80 bringing total to
£400"
I am speechless - this is clearly a guy who should know the day rate of any tradesman and then been treated like this.
For me it isn't just only a few hours extra as it is time wasted not being notified to secure other jobs (as clearly knowing the job was delayed to start with), extra time spend going forth and back for 6 days rather than 3 (outside city), not to mention cut in day rate to less than National Minimum Wage for this guy!:7:
Sorry for the rant...
Has any of you experienced this? How did you react to it?
Was £120 really too much to ask for? :huh2:
Cheers,
Stina (not the tiler I have to say)
This is the first time I have been this annoyed with tradesmen...
A plumber we have been doing works for in the past had two jobs we quoted for a long while ago. The one job was finally ready to start 29th but got a text very late (11pm) Sunday night (only after chasing him since Friday 26th) saying the job wasn't ready until Thursday!
Needless to say it was too late to arrange another job for start Monday morning, so emailed another customer saying that the job we had booked in later the week could start already Tuesday. So far so good, other than this customer wasn't ready and then went ahead to book another tiler! So two jobs down... as in lost!
The plumber's job supposing to start 2nd July was again delayed one day, to start Friday 3rd! Again late night Thursday a text informed that the job wouldn't be ready until Saturday AFTERNOON! Who are to start a job at that time may I ask? :incazzato:
Well, started the job Monday morning 6th July - one week delayed without other jobs booked in the time wasted due to poor information from this plumber guy!
The kitchen splashback and floor was suppose to take 2-2.5 days max. It developed into taking a FULL week, finishing grouting Saturday mid day!!! :yikes: It turned out that when starting on tiling the splashback the worktop not entirely installed, so this would only be finish 5 days later on Saturday.
All of a sudden the hallway was to be tiled as well (not a problem as underfloor heating in kitchen wasn't installed as promised). Was told late Tuesday when requesting an update that this would be done Wednesday, so leaving us with another wasted day without enough notice given to take on another job. :juggle2:
The underfloor heating was then suppose to be in place to start tiling in the morning of Thursday - went on site only to find the house locked and the plumber not arriving until 9.30 starting to lay the underfloor heating!!!
Assisted laying the UFH as nothing else to do. Started tiling at noon! Went back Friday to finish floor and grout the hallway. Only to having to return Saturday to finish the splashback as worktop then installed.
Original quote accepted was £320. Was told by the plumber to charge extra as the 3 sq meter hallway wasn't included in quote. Did so and added a bit extra for assisting laying the underfloor heating, in total £120 extra (with a reminder to the plumber that the job had been delayed a week and taken twice the time).
Now I have just received this email from him saying:
"Extra costs of £130 i find to be a little excessive for the extra few hours
that the job went over. I am willing to pay extra £80 bringing total to
£400"
I am speechless - this is clearly a guy who should know the day rate of any tradesman and then been treated like this.
For me it isn't just only a few hours extra as it is time wasted not being notified to secure other jobs (as clearly knowing the job was delayed to start with), extra time spend going forth and back for 6 days rather than 3 (outside city), not to mention cut in day rate to less than National Minimum Wage for this guy!:7:
Sorry for the rant...
Has any of you experienced this? How did you react to it?
Was £120 really too much to ask for? :huh2:
Cheers,
Stina (not the tiler I have to say)