Gentlemen,
Thanks for all your replies and advice.
I've had one tiler quote for the job. He certainly wasn't cheap but as most of you said, "don't expect a cheap price".
I was surprised that he said it would take between 8 and 9 days for two of them to lay the floor. Effectively this is 16 -18 man days; I thought it would have taken less time than that?
Thanks for all your replies and advice.
I've had one tiler quote for the job. He certainly wasn't cheap but as most of you said, "don't expect a cheap price".
I was surprised that he said it would take between 8 and 9 days for two of them to lay the floor. Effectively this is 16 -18 man days; I thought it would have taken less time than that?