Hi,
So Im laying UFH (warm-up) in my bathnroom.
Ive covered joists with 18mm wbp ply which will be primed, then 2mm flexi adhesive,then 6mm insulation boards, then 2mm UFH, I am then going to self level over top - how much I'm not sure but would say 3mm.
Ill then tank then adhesive and then tile.
My problem is, that if I do all this my floor will be raising up about 20mm! Do you guys think thats acceptable?
Could I lose the insulation boards?
Is UFH really worth it? - any opinions?
Is there anything that ive listed that you guys thinbk I could get rid of to bring the floor level down.
Thanks
Mark
Plumber
So Im laying UFH (warm-up) in my bathnroom.
Ive covered joists with 18mm wbp ply which will be primed, then 2mm flexi adhesive,then 6mm insulation boards, then 2mm UFH, I am then going to self level over top - how much I'm not sure but would say 3mm.
Ill then tank then adhesive and then tile.
My problem is, that if I do all this my floor will be raising up about 20mm! Do you guys think thats acceptable?
Could I lose the insulation boards?
Is UFH really worth it? - any opinions?
Is there anything that ive listed that you guys thinbk I could get rid of to bring the floor level down.
Thanks
Mark
Plumber