UFH is glued down and planning to do self levelling compound and tile shortly after.
The area is roughly 6m2 and includes walkin shower which im putting UFH in also
Is the plan below ok?
1. use studs to block areas
2. use 3 bags of FIBREPLAN pour and level using TROWEL about the same height as UFH cables (2-3mm)
3. Leave to dry
4. use BAL RAPIDSET FLEXIBLE ADHESIVE mixed with MAPEI LATEX PLUS over UFH in walkin shower bit and smooth to falls using TROWEL
5. leave to dry
6. Everything dry, use more BAL RAPIDSET FLEXIBLE ADHESIVE for porcelin tiles
any thing im missing or got wrong here guys?
Thanks for help
UFH is glued down and planning to do self levelling compound and tile shortly after.
The area is roughly 6m2 and includes walkin shower which im putting UFH in also
Is the plan below ok?
1. use studs to block areas
2. use 3 bags of FIBREPLAN pour and level using TROWEL about the same height as UFH cables (2-3mm)
3. Leave to dry
4. use BAL RAPIDSET FLEXIBLE ADHESIVE mixed with MAPEI LATEX PLUS over UFH in walkin shower bit and smooth to falls using TROWEL
5. leave to dry
6. Everything dry, use more BAL RAPIDSET FLEXIBLE ADHESIVE for porcelin tiles
any thing im missing or got wrong here guys?
Thanks for help