S
stevetalbot
Hi, can anyone give any advice on a tiling job which I have had done.
I supplied the tiles (White Jerusalem Marble) adhesive and grout (ordered sealer but did not arrive).
The tiles were laid in a new kitchen of about 20sq mtrs. I had ordered enough for the tiles to be laid first before the kitchen was installed but was told that the kitchen needed to be fitted first because the island could not be fixed on top of the underfloor heating - I would have thought that the underfloor heating could have been laid to go around where the island was to be located as we had a plan - we are now left with cuts up to end panels and around posts etc and the job took alot longer because of all the cuts.
The tiler took 4 days and we were advised each night not to stand on certain areas which had been laid kate in the day.
After the 4 days he had one tile to cut and various tiles to fix (mainly cuts around the island. As this was Friday we were left over the bank holiday weekend and used the kitchen as normal (we were told that we could).
The tiles were not sealed and over the weekend the tiles became very marked and these marks cannot be removed.
My question is this - should the tiles have been left for this length of time without sealing? The tiler came back on the Tuesday - fitted the loose tiles and left without grouting or offering any help. We have now received his invoice which we have not yet paid.
The supplier of the tiles says that they need grinding on site and this will cost £45 to £50 per metre plus VAT. I have told the tiler and he says that they can be cleaned but expects me to pay.
Any advice?
I supplied the tiles (White Jerusalem Marble) adhesive and grout (ordered sealer but did not arrive).
The tiles were laid in a new kitchen of about 20sq mtrs. I had ordered enough for the tiles to be laid first before the kitchen was installed but was told that the kitchen needed to be fitted first because the island could not be fixed on top of the underfloor heating - I would have thought that the underfloor heating could have been laid to go around where the island was to be located as we had a plan - we are now left with cuts up to end panels and around posts etc and the job took alot longer because of all the cuts.
The tiler took 4 days and we were advised each night not to stand on certain areas which had been laid kate in the day.
After the 4 days he had one tile to cut and various tiles to fix (mainly cuts around the island. As this was Friday we were left over the bank holiday weekend and used the kitchen as normal (we were told that we could).
The tiles were not sealed and over the weekend the tiles became very marked and these marks cannot be removed.
My question is this - should the tiles have been left for this length of time without sealing? The tiler came back on the Tuesday - fitted the loose tiles and left without grouting or offering any help. We have now received his invoice which we have not yet paid.
The supplier of the tiles says that they need grinding on site and this will cost £45 to £50 per metre plus VAT. I have told the tiler and he says that they can be cleaned but expects me to pay.
Any advice?