johnw100
Hi All
I`m having a shower room refitted and have decided to have the shower area tanked. The guy who removed all the old bathroom is telling me he cant tank the wall for a few weeks due to other work and it`ll take 2 months to dry before tiliing can commence. The room is unheated but it seems ridiculous amount of time for it to dry.
Any ideas?
Thanks
John
I`m having a shower room refitted and have decided to have the shower area tanked. The guy who removed all the old bathroom is telling me he cant tank the wall for a few weeks due to other work and it`ll take 2 months to dry before tiliing can commence. The room is unheated but it seems ridiculous amount of time for it to dry.
Any ideas?
Thanks
John