Evening all,
I have a wetroom install & tile coming up which we have done before however it was some years back.
It is 1st floor extension so in effect a new build.
The small wetroom is currently studded out ready to receive boarding.
Apparently the plumber has installed an Impey shower tray on 18mm marine ply.
I am just looking for confirmation on the correct process after that.
The tray is 22mm and the ply obviously 18mm making 40mm which we have to build up to.
I initially wanted to lay 18mm onto joists followed by 10mm Dukka board and a UFH mat with screed at 3-5mm.
Obviously that only equates to 33mm max.
So my questions are
a) When do I tape the Dukka to the tray
b)Should I make up the level with a thicker screed or additional ply on top of the 18mm marine?
Any help would be greatly appreciated.
I have a wetroom install & tile coming up which we have done before however it was some years back.
It is 1st floor extension so in effect a new build.
The small wetroom is currently studded out ready to receive boarding.
Apparently the plumber has installed an Impey shower tray on 18mm marine ply.
I am just looking for confirmation on the correct process after that.
The tray is 22mm and the ply obviously 18mm making 40mm which we have to build up to.
I initially wanted to lay 18mm onto joists followed by 10mm Dukka board and a UFH mat with screed at 3-5mm.
Obviously that only equates to 33mm max.
So my questions are
a) When do I tape the Dukka to the tray
b)Should I make up the level with a thicker screed or additional ply on top of the 18mm marine?
Any help would be greatly appreciated.