Hi folks I am hoping to get some expert advice here on how to ensure my floor is properly prepped for the soon to be installed Impey Aqua Dec. Here's a spec I've drawn up from instructions / videos / this forum Sorry its so long but I'd very much appreciate any pointers people have on this as I'd like to make sure its done as well as possible. I have no DIY expertise as will be obvious reading this lol! I'm just paying for it!
1. Remove existing floorboards
2. Reinforce existing joists – how do I determine if this needs done at all, and if it does, what exactly to do? Joiner will err on the side of ‘it’ll be fine’ so I’ll need to know!
3. Use noggins where needed – does this only apply if joists spaced > 600mm? Floor hasn’t been lifted yet so I don’t know what the set up is at the moment.
4. Use Celotex FF3000 insulation board between joists
5. Install trap part of the floor gully & connect to waste
6. Lay new WBP ply floor – 22 mm screwed at 300mm centres – does this have to be coated in something above / below?!
7. Cut out a section of this ply for the 1m x 1m Impey aqua dec
8. Attach battens to existing joists & use 18mm ply to create platform for dec
9. Add noggins to support all 4 sides of dec
10. Install dec – screw to joists
11. Create groove for UFH sensor in floor – cut channel in ply for this near the timer control
12. Apply single-part flexible cement based adhesive to dry clean floor.
13. Tank floor (& up walls 75mm) with TileSafe
14. Use Dural WP or other tanking system on 2 shower walls
15. Install DEVI mat directly onto TileSafe membrane
15. Apply SLC then tile
There will be a new stud wall built which the shower head will be on. Should I use Wedi board to construct the new stud wall & to box in the bath, or PB and a tanking membrane? The stud wall will incorporate 3 recesses, 1 of which is in the shower area – might be difficult to tank a recess with membrane? Would Bal WP1 be better to use in this case?
Thanks in advance for your time
1. Remove existing floorboards
2. Reinforce existing joists – how do I determine if this needs done at all, and if it does, what exactly to do? Joiner will err on the side of ‘it’ll be fine’ so I’ll need to know!
3. Use noggins where needed – does this only apply if joists spaced > 600mm? Floor hasn’t been lifted yet so I don’t know what the set up is at the moment.
4. Use Celotex FF3000 insulation board between joists
5. Install trap part of the floor gully & connect to waste
6. Lay new WBP ply floor – 22 mm screwed at 300mm centres – does this have to be coated in something above / below?!
7. Cut out a section of this ply for the 1m x 1m Impey aqua dec
8. Attach battens to existing joists & use 18mm ply to create platform for dec
9. Add noggins to support all 4 sides of dec
10. Install dec – screw to joists
11. Create groove for UFH sensor in floor – cut channel in ply for this near the timer control
12. Apply single-part flexible cement based adhesive to dry clean floor.
13. Tank floor (& up walls 75mm) with TileSafe
14. Use Dural WP or other tanking system on 2 shower walls
15. Install DEVI mat directly onto TileSafe membrane
15. Apply SLC then tile
There will be a new stud wall built which the shower head will be on. Should I use Wedi board to construct the new stud wall & to box in the bath, or PB and a tanking membrane? The stud wall will incorporate 3 recesses, 1 of which is in the shower area – might be difficult to tank a recess with membrane? Would Bal WP1 be better to use in this case?
Thanks in advance for your time