I been asked to tile a full bathroom floor and all , so i went to view, its a nice
empty shell at the moment, any how the plumber was there so while talking to
the customer about starting i said well once the plumber puts the bath in i can
make a start, the plumber then said no mate you tile the floor first so i can then
put my bath in and get the bath panel correct, i said i do the floor last once the
walls are all done, he then said well thats not how they do it on sites.
have i gone backing mad or is this plumber right, if so then i may hang up my
trowel
shaun ..........
empty shell at the moment, any how the plumber was there so while talking to
the customer about starting i said well once the plumber puts the bath in i can
make a start, the plumber then said no mate you tile the floor first so i can then
put my bath in and get the bath panel correct, i said i do the floor last once the
walls are all done, he then said well thats not how they do it on sites.
have i gone backing mad or is this plumber right, if so then i may hang up my
trowel
shaun ..........