ok so im on a job with 3 bathrooms to go at. Ive got 2 of them prepped with deltaboard 6mm,ufh,self level and waterproof. i came to start the floor in the main bathroom saturday and the tiles for it had been delivered. i cracked on and got the majority of the floor down before the customer arrived and said the tile was too dark and the wrong colour. so he decided to take them up which i did and he paid me a days wage for it. but with the adhesive going close to set i had to scrape/chip it all up and accidently nicked an ufh cable. so now an engineer has to come out from Warmup to fix it. we agreed to go halves on the cost but after the weekend i believe the tile shop who delivered the wrong tiles should be paying the customer for my labour and the engineer to fix it as it was their original mistake who created the problem.
Thoughts please?? im i right or wrong??
Thoughts please?? im i right or wrong??