Tiling floor preparation

Tilers Forums Official Sponsors

We've had a builder prepare the kitchen floor ready for tiling which he will be doing

The kitchen is empty with the skirting all removed

The tiles will either be ceramic or porcelain tiles

The kitchen is a part suspended timber floor with floorboards which has little to no bounce/movement and the other half of the kitchen is a concrete floor.

He has has carried out the following work so far as per the works schedule he has provided

- Applied BAL SBR Bond to all the faces of the plywood including sides, 2 coats

- 5.5mm plywood with staggered joints laid down using 4 x 40mm screws at every 100 to 150mm centres

On the concrete side he has stated no preparation is required

He has advised he'll be using an S1 or S2 flexible floor adhesive

For peace of mind can anyone tell me what he is doing is correct
 
Last edited:
Yes seriously .
View it this way , you're happy to let a builder tile but would you be happy to let a tiler renovate your house .
 
The house requires considerable work, some of the jobs he's sub contracted out to other contractors whereas the tiling he said he could do and has done many times previously
[automerge]1572379513[/automerge]
I presume the fact that he has used plywood is wrong? Has he done anything else incorrectly?
 
I'm not getting funny with you just trying to make a point .
This builder see' s other trades as specialist that he needs to subcontract out but not tiling because anybody can do it , and you must agree because you're letting him , but you had doubts straight away or you wouldn't be here . I'm getting mixed messages .
 
I'm not getting funny with you just trying to make a point .
This builder see' s other trades as specialist that he needs to subcontract out but not tiling because anybody can do it , and you must agree because you're letting him , but you had doubts straight away or you wouldn't be here . I'm getting mixed messages .

I understand and totally see where you are coming from, it's only after he fitted the plywood where I was doubting whether it was correct as it was quite flimsy, however as he's screwed it down every 150mm it seems pretty solid. But having said that from what I've been told here and researching its wrong 🙁
 
Has he mentioned his plan of action where to the two different substrates meet? 🤔

Yep he mentioned fitting an expansion joint between the solid and timber floor
[automerge]1572381334[/automerge]
I will speak to him tomorrow, could someone kindly outline the steps and correct materials required to undertake this correctly
 
Last edited:

Advertisement

Thread Information

Title
Tiling floor preparation
Prefix
N/A
Forum
Canada Tile Advice
Start date
Last reply date
Replies
37

Advertisement

UK Tiling Forum

Thread statistics

Created
ash2710,
Last reply from
ash2710,
Replies
37
Views
7,242

Thread statistics

Created
ash2710,
Last reply from
ash2710,
Replies
37
Views
7,242

Weekly Email Digest

Back