LauraDean
TF
Hi, we have a half roll top bath (so is a straight edge and connected to the wall on two sides, but doesn't have a panel).
Picture below:
Our tiler and our plumber are saying two different things and I don't know what is best.
Our plumber is saying he isn't happy with the walls being tiled floor to ceiling first and then the bath being fitted up to it, as he doesn't feel just a Silicon seal would be enough. He is suggesting the bath be fitted and the tiler tile to the bath and then underneath on the bits he can do. I personally think this is impossible to tile under the bath once in?
The tiler is saying that you tile the whole wall and then fit the bath.
To add to the complication, we would like a herringbone tile pattern!
Please could I have any advice? I'm torn between the two at the moment
Picture below:
Our tiler and our plumber are saying two different things and I don't know what is best.
Our plumber is saying he isn't happy with the walls being tiled floor to ceiling first and then the bath being fitted up to it, as he doesn't feel just a Silicon seal would be enough. He is suggesting the bath be fitted and the tiler tile to the bath and then underneath on the bits he can do. I personally think this is impossible to tile under the bath once in?
The tiler is saying that you tile the whole wall and then fit the bath.
To add to the complication, we would like a herringbone tile pattern!
Please could I have any advice? I'm torn between the two at the moment