2
2020Tiling
hi ! i stupidly priced a job up last week which i got and have underestimated the price and time of job! price was to tile bathroom half height walls (12mtrs) and 4mtrs floor. floor was chip board, tiles are ceramic (pics to follow!) wen i priced the job i was told he was getting 8 by 6 inch tiles 4 walls , so as i no the lad and had a few tubs of addy in my garage i thought id give him a good price and be in and out in 2 days ! problem is (and i no its my fault as iam crap at pricing) wen i arrived at the job he had got large format tiles so couldn't use my tubbed addy i had in garage! also wen i priced the job i was gonna put ply down that i also have in my garage !plus 6mm trims i had . to cut a long storey short ive basically tiled the lot inc buying hardy backer board ,10mm trims + 4 bags of rapid and grout and 200 30mm hardy screws and a scribe plus scrim out of my measly quote! and have had a nightmare with the walls and my cutters broke etc. the total amount iam getting 4 job less materials is >>>> 70 pound :yikes:. my problem is do i put it down to experience and me being crap at quotes ! or do i confront the customer and tell him i buggered up big time with the price ? job is looking great by the way but has taken a lot longer.