First off hello to all.
Now my question is-
I have a impatient customer who is putting pressure on me to tile before my plaster has had time to dry out properly, I had to bond out two walls and windows and skim both. I put up aqua board from where the bath end would be just so i could get the bath/shower in and tiled( the bath side was a stud wall so no problems). its been a week since i did all the plastering, I told them I would tile the 2 plastered walls 3 weeks from then but they want it done before the grankids come to stop this coming weekend, what do you do just go ahead and tile to keep em happy or stick to what I recomended?
 
hi belli,if you think you need more time for it to dry then they must wait.....if they dont want to wait bill them for your services and move on is my advice

you have the correct attitude
 
Your talking bonding which was probably applied to a pva to stop any suction so drying time would increase, leave it to your recommended drying time..
 
Hi and welcome. make sure there is plenty of ventilation, and see how it goes, but do not tile while still wet.
 

Advertisement

Thread Information

Title
Hello and a quick question.
Prefix
N/A
Forum
UK Tiling Forum
Start date
Last reply date
Replies
4

Thread Tags

Advertisement

UK Tiling Forum

Thread statistics

Created
Belli,
Last reply from
Ian,
Replies
4
Views
703

Thread statistics

Created
Belli,
Last reply from
Ian,
Replies
4
Views
703
Back