Hi,
I've just joined to ask for an opinion on the following situation.
We are in the process of having a new bathroom, which is slow progress due to a number of problems with the fitters, (6 weeks so far, for a 12 day job.) The first guy working on the job was sacked by the boss for a number of **** ups, the main one being installing the shower valve upside down (the plate was etched, so unfortunately it mattered.) Anyway, the boss has carried on now (after 2 weeks of no work while we waited for him.)
In the process of correcting the valve he obviously had to remove a number of tiles from the shower area. Ultimately this now means that he has run out of tiles for the job and has bought some more (it was a 100% supply and install agreement including the tiles). The pictures show some of the new tiles that have been fitted so far - which obviously look like a different batch. He has attached these on all 4 walls in places - and there is still a fairly large area left to tile with the new lot as well.
We pointed this out to him after the days work, and unfortunately he decided to quit the job as we had "unobtainable standards". This is combined with other outstanding issues from the previous guy he sacked (eg. scratch in bath and on waste, poor plastering around light fittings plus some other things we were originally promised will be sorted when we pointed them out.) He is always a little argumentative when we mention a problem by blaming us for the issues, even though they were caused by his fitter.
The fitter has since requested that he carries on the job, repairing the issues with the bath etc, although he is obviously not keen on correcting the tiles saying that it would damage the plasterboard if they were removed.
We have tried to be reasonable all the way through this process, but we would like some further advice on what we should do next. Should we give the guy an opportunity to carry on, and if so should we be expecting him to replace the tiles to match. (This may be problematic as the first fitter appears to have disposed of all the boxes in the skip which has now been collected so I doubt he could find the batch number?) There is £1500 remaining to pay, and the guy originally said we can use that to get someone else to finish it. However if new tiles and fitting is required it would cost a lot more than that. I don't think I am comfortable accepting the miss-matched tiles as they are obvious, but your advice would be appreciated.
Sorry for the long post, and thanks in advance. I can't appear to upload photos, so I've linked to a folder on my OneDrive:
tilersforum
I've downloaded from your one drive and inserted them.
I've just joined to ask for an opinion on the following situation.
We are in the process of having a new bathroom, which is slow progress due to a number of problems with the fitters, (6 weeks so far, for a 12 day job.) The first guy working on the job was sacked by the boss for a number of **** ups, the main one being installing the shower valve upside down (the plate was etched, so unfortunately it mattered.) Anyway, the boss has carried on now (after 2 weeks of no work while we waited for him.)
In the process of correcting the valve he obviously had to remove a number of tiles from the shower area. Ultimately this now means that he has run out of tiles for the job and has bought some more (it was a 100% supply and install agreement including the tiles). The pictures show some of the new tiles that have been fitted so far - which obviously look like a different batch. He has attached these on all 4 walls in places - and there is still a fairly large area left to tile with the new lot as well.
We pointed this out to him after the days work, and unfortunately he decided to quit the job as we had "unobtainable standards". This is combined with other outstanding issues from the previous guy he sacked (eg. scratch in bath and on waste, poor plastering around light fittings plus some other things we were originally promised will be sorted when we pointed them out.) He is always a little argumentative when we mention a problem by blaming us for the issues, even though they were caused by his fitter.
The fitter has since requested that he carries on the job, repairing the issues with the bath etc, although he is obviously not keen on correcting the tiles saying that it would damage the plasterboard if they were removed.
We have tried to be reasonable all the way through this process, but we would like some further advice on what we should do next. Should we give the guy an opportunity to carry on, and if so should we be expecting him to replace the tiles to match. (This may be problematic as the first fitter appears to have disposed of all the boxes in the skip which has now been collected so I doubt he could find the batch number?) There is £1500 remaining to pay, and the guy originally said we can use that to get someone else to finish it. However if new tiles and fitting is required it would cost a lot more than that. I don't think I am comfortable accepting the miss-matched tiles as they are obvious, but your advice would be appreciated.
Sorry for the long post, and thanks in advance. I can't appear to upload photos, so I've linked to a folder on my OneDrive:
tilersforum
I've downloaded from your one drive and inserted them.
Last edited by a moderator: