Arms
Wot are the drying times for screed with piped UFH

I was always under the impression that it is around 25mm per week.........or is that bull😕

Builder is laying 65mm onto pipes soon.......and punter wants it tiled as soon as.
 
hi CJ mate.. your right on your dryin times . on average its usualy 30 days...
If you want to tile earlier then you can use the schluter ditra system as this will allow the screed to dry out from underneath the mat... Or you could use bal green screed adhesive which i think is your best option as it will be cheaper than ditra....heres a link for bal green screed tech info.............dave.....Green Screed Adhesive

p.s. there is also a commission period before you should turn the UFH on so check with bal before you allow customer to turn it on.....
 
Last edited by a moderator:
wots the trade price for that Gaz?

I have used it a few times before...........but not got the price of the stuff
 

Advertisement

Thread Information

Title
Screed drying times.
Prefix
N/A
Forum
UK Tiling Forum
Start date
Last reply date
Replies
3

Thread Tags

Advertisement

Tilers Forums Official Sponsors

Thread statistics

Created
CJ,
Last reply from
CJ,
Replies
3
Views
5,546

Thread statistics

Created
CJ,
Last reply from
CJ,
Replies
3
Views
5,546
Back