Right, when people say not to tile until the UFH has been commissioned, does this mean, joined up to the electrics and fired up first? I'm Installing UFH for the first time next week, and I plan on installing then covering with SLC. The UFH will not be joined up to the mains for perhaps another 2 weeks as the spark is busy working away atm.
I dont see this being a problem aslong as the matting is tested before, during and after installation, and then after a good 2 weeks after floor is finishad and once the sparky is free to slowly worked up to temperature bit by bit...
I dont see this being a problem aslong as the matting is tested before, during and after installation, and then after a good 2 weeks after floor is finishad and once the sparky is free to slowly worked up to temperature bit by bit...