Discuss underfloor heating - tile moving dilemma in the UK Tiling Forum area at TilersForums.com.

D

Daz

Wow lucky you! There's loads of top quality guys near you. If it goes slightly "pear shaped" you won't have trouble finding someone from here to assist. Phil Hobson springs to mind but I know there are quite a few established members on here that are more than capable of providing an assessment, if it comes to it.

Daz
 
G

gubbins

Wow lucky you! There's loads of top quality guys near you. If it goes slightly "pear shaped" you won't have trouble finding someone from here to assist. Phil Hobson springs to mind but I know there are quite a few established members on here that are more than capable of providing an assessment, if it comes to it.

Daz

Great! that's very reassuring to know Daz.
 
G

gubbins

Meeting later today so Im looking for further clarification on some points;

If the 'Thermomix UHFL' dial was kept on the minimum setting during the 4 days or so the tiled floor was heated do the thermostic controls on the various zones have any / much effect on the heat that is applied to the UFH? They were up at 27C for the whole 4 days with the thermomix set at minimum.
If as timeless john mentions you should increase the thermostat by 5C steps, is that the thermomix dial or the thermosatic controls on the various zones? How long should each 5C increment be maintained for? And is it then ran at 4 days once at maximum?

Does performing this incorrectly alter the nature of the adhesive and / or anything else?

Thanks again you guys.

gubbins
 
T

Time's Ran Out

If I'am allowed to quote - from a major adhesive manufacturers 'bible'.

The heating pipes should be installed according to manufacturers instructions, fixed down and tested prior to being encapsulated in a screed or levelling compound.
If the pipes have been laid in a reinforced sand/cement screed, this must be allowed to dry fully prior to tiling.
A sand/cement screed should be left for 3 weeks with the underfloor heating off, to dry.
After this period the heating system should be turned on and the temperature raised by a maximum of 5degrees/day until the maximum recommended operating temperature is achieved.
This temperature should be maintained for 3 days and then the system turned off and the screed allowed to cool to 15degrees before tiling commences.

If a suitable polymer-modified levelling compound is used to cover the pipes instead of a sand/cement screed, the drying time will be considerably shorter.

Ensure that the cured surface of the floor is rigid, sound, clean, dry and free from any contaminating barrier. Porous or dense substrates must be primed and also impervious surfaces with the relevant manufacturers primers.

Fix the tiles.

Allow to cure. Keep the warming system turned off for at least 5 days to allow the cement to cure. Bring the system up to its operating temperature gradually in stages of 5degrees/day.



I hope this is of help.
You need to obtain the exact type of screed laid and the preparation prior to tiling it received

:thumbsup:
 
G

gubbins

If I'am allowed to quote - from a major adhesive manufacturers 'bible'.

The heating pipes should be installed according to manufacturers instructions, fixed down and tested prior to being encapsulated in a screed or levelling compound.
If the pipes have been laid in a reinforced sand/cement screed, this must be allowed to dry fully prior to tiling.
A sand/cement screed should be left for 3 weeks with the underfloor heating off, to dry.
After this period the heating system should be turned on and the temperature raised by a maximum of 5degrees/day until the maximum recommended operating temperature is achieved.
This temperature should be maintained for 3 days and then the system turned off and the screed allowed to cool to 15degrees before tiling commences.

If a suitable polymer-modified levelling compound is used to cover the pipes instead of a sand/cement screed, the drying time will be considerably shorter.

Ensure that the cured surface of the floor is rigid, sound, clean, dry and free from any contaminating barrier. Porous or dense substrates must be primed and also impervious surfaces with the relevant manufacturers primers.

Fix the tiles.

Allow to cure. Keep the warming system turned off for at least 5 days to allow the cement to cure. Bring the system up to its operating temperature gradually in stages of 5degrees/day.



I hope this is of help.
You need to obtain the exact type of screed laid and the preparation prior to tiling it received

:thumbsup:

The screed was lafarge gyvlon : Lafarge Gyvlon Anhydrite based Calcium Sulphate Flowing Screed i'll find out more when we meet in a few days (last one was postponed as one crucial person was held up ) what i'm still needing clarification on is when they are talking about increasing the temperature in 5C increments is that the control (miramix) near to the mainifold that has min- 40-45-50 etc on it or the thermostatic controls dials on on each zone? Like ive mentioned already a couple of times the miramix was set on 'minimum' for 4 days (post tiling but not grouted) but the thermostat dials were put immediately and left on 27C. Was this wrong or does only the miramix setting matter in this case? Is there another section of the forum more suitable for me to post this UFH question as id really like the answer before we meet after the weekend?
Thanks again. Gubbins
 
G

gubbins

might be bed time for me ///but what type of screed is it ,and has the tiler allowed expansion joints especially around the perimeter being a large floor it must have expansion if not this could be the problem

Thanks Jay, im sure i recall seeing the expansion materials around the perimeter as recommended on the lafarge gyvlon downloads; the tiles themselves have expansion joints within a couple of door thresholds separating sizeable rooms. Thanks
 
G

gubbins

And the sizeable rooms have expansion joints in them separate to the doorway ones

Not visible to me within the tiling Jay. although the same materials, tiler and UFH have been used in rooms of much smaller size/ ie <2m - <3 m in length / breadth and one of those rooms already has a tile that very occasionally makes a very slight sound when walked on.
 
G

gubbins

It may be a part of the problem and might be worth taking note of ,Lack of expansion joints on a large floor with heating can cause failure . With lack of good prep work and priming. Leaves a lot of room for failure . please keep us updated on this one thanks

jay

Oh I have the feeling given the cost of remedying the problem this one is going to run and run so I will do, thanks Jay
 

Ajax123

TF
Esteemed
Arms
932
1,213
Lincolnshire
Hi gubbins.

This may be nothing whatever to do with the heating even thouh technically it hould b switched off, there are different schools of thought ref this. One is that the screed shold be unheated. The problem with this is that th screed will naturally expand anc contrct with ambient changes. The counter argument is that if the s creed is heated to a constant temperature of about 20 degrees c during tling this is not only the optimum temp for tile aheives and primers it also holds the screed at a constant temp therefor expansion and contraction is eliminated.

Now then. Question for you....with what was the screed primed and how was this applied
 
D

Daz

Not visible to me within the tiling Jay. although the same materials, tiler and UFH have been used in rooms of much smaller size/ ie <2m - <3 m in length / breadth and one of those rooms already has a tile that very occasionally makes a very slight sound when walked on.

What sort of noise is it?
I may be way off track here, but I do have that niggling feeling that a decoupling mat has been used &, unfortunately, failed.

Daz
 

tommyzooom

TF
Arms
87
1,083
Ireland
I'm not a plumber, but re the heating controls, In my opinion, the way yours was controlled is the way I would do it, The mixing stat set to minimum, won't allow water higher than (for an example)10 degrees past this point into your floors,
Room stats are little more than an On/Off switch, setting these at 27 degrees will mean that , as the floor/room will probably never reach this temp, they will remain open and "calling" for heat all the time. You could then raise the temp gradually at the mixer stat.

However the heating should remain off during tiling and grouting, and remain off for up to 14 days after completion of grouting,
 

Reply to underfloor heating - tile moving dilemma in the UK Tiling Forum area at TilersForums.com

Subscribe to Tilers Forums

There are similar tiling threads here

    • Like
Hello, I did some reading here and there, but the opinions seem to diverge at some point and I...
Replies
2
Views
1K
    • Like
Hi guys. Im a carpenter who has tiled a fair few floors over the years as i fit a lot of...
Replies
13
Views
2K
Hi All I am after some advice please. We have a retrofit undefloor heating system ( Robbens...
Replies
8
Views
4K
I had a small leak in the main water line before the stop tap in my 1950s house. The copper pipe...
Replies
1
Views
2K
Tiling a new extension. Cement poured screed on piped underfloor heating. Heating has been...
Replies
3
Views
2K

Trending UK Tiling Threads

UK Tiling Forum Popular

Advertisement

Thread Information

Title
underfloor heating - tile moving dilemma
Prefix
N/A
Forum
UK Tiling Forum
Start date
Last reply date
Replies
46

Which tile adhesive brand did you use most this year?

  • Palace

    Votes: 5 4.5%
  • Kerakoll

    Votes: 8 7.1%
  • Ardex

    Votes: 7 6.3%
  • Mapei

    Votes: 32 28.6%
  • Ultra Tile

    Votes: 14 12.5%
  • BAL

    Votes: 29 25.9%
  • Wedi

    Votes: 3 2.7%
  • Benfer

    Votes: 2 1.8%
  • Tilemaster

    Votes: 19 17.0%
  • Weber

    Votes: 18 16.1%
  • Other (any other brand not listed)

    Votes: 13 11.6%
  • Nicobond

    Votes: 5 4.5%
  • Norcros

    Votes: 3 2.7%
  • Kelmore

    Votes: 2 1.8%

You're browsing the UK Tiling Forum category on TilersForums.com, the tile advice website no matter which country you reside. Our UK based online tiling forum has 48,000 members and started out in 2006.

Top