trevortine
So I'm pricing up a job just now and the architect has specd up 2500x600x10mm wedi board over chipboard, electric heating over that and then tiled. Apart from the fact he has missed out slc over cables I cannot see this being viable. The addy choice between chipboard and wedi was Mapei ultra flex, an s2 adhesive albeit but when I mention mechanical fixings on top, ie wedi washers and screws they say no need? There's 50m2 of this to do and I need it to be 100%. I recommended fitting hardie to chipboard first and then insulation but there is height issues, as well as the extra cost. Have priced up both options and there is a considerable difference, any thoughts, would you do this?