JOHNNYCLARKE
sully
sand/cement screed has different drying time to anhydrite. The BS has changed in last few years and is something like 25mm for 1st week and then 1mm a day thereafter.
I always work on a month but that is me not the ruling.
You will find very few contractors stick to the new regs as it is simply too long for them to wait.
And the other main difference is you definitely can put ditra down on screed as soon as you can walk on it so say schluter. I always say min 5 days.
You can check any of this info by calling the technical dept of your adhesive manufacturer provided they are a big outfit set up for it.
My problem was it being weekend and getting one piece of advice from a tech dept and then hearing more detailed info on this forum that I cannot check till monday.
Johnny
sand/cement screed has different drying time to anhydrite. The BS has changed in last few years and is something like 25mm for 1st week and then 1mm a day thereafter.
I always work on a month but that is me not the ruling.
You will find very few contractors stick to the new regs as it is simply too long for them to wait.
And the other main difference is you definitely can put ditra down on screed as soon as you can walk on it so say schluter. I always say min 5 days.
You can check any of this info by calling the technical dept of your adhesive manufacturer provided they are a big outfit set up for it.
My problem was it being weekend and getting one piece of advice from a tech dept and then hearing more detailed info on this forum that I cannot check till monday.
Johnny