Just wondering if this is correct process for UFH installation ? Not me doing it , just want to check method is correct.
Sub is 80% Concrete 20% covered in minimal layer of latex based slc.
The plan is to
1) Prime sub
2) apply spf and lay 6mm thermal boards staggered.
3) lay out matting and test, then stick down using self adhesive backing.
4) Cover in weber floor flex. been reccommended 10mm covering off weber technical
5) prime
6) weber set plus rapid adhesive to fix.
This sound ok?
Thanks.
Just wondering if this is correct process for UFH installation ? Not me doing it , just want to check method is correct.
Sub is 80% Concrete 20% covered in minimal layer of latex based slc.
The plan is to
1) Prime sub
2) apply spf and lay 6mm thermal boards staggered.
3) lay out matting and test, then stick down using self adhesive backing.
4) Cover in weber floor flex. been reccommended 10mm covering off weber technical
5) prime
6) weber set plus rapid adhesive to fix.
This sound ok?
Thanks.