ive been helping my pal out who runs is own comp doing concrete reinforced construction.
working in leeds st marks new uni campus
i deffo wont be making this my new career, started wednesday , laying visqueen and doing insulation that was easy , then helping fixers do the reinforced steel work that was ok , boxing pipes before concrete arrives ,
pump arrives , followed by concrete , wellies on im ready, pushing and pulling concrete , then on poker taking all the air out
63 m3 done and im buggered , then my other pal who is the foreman c,mon rob just got 2 walls to pour then were done about 10m3
slept like a baby that night
thursday same again but this time no pump ,concrete poured into large bucket of 1 of the diggers , then poured were he could reach
,back breaking work another 60m3 poured and ive about had it
working in leeds st marks new uni campus
i deffo wont be making this my new career, started wednesday , laying visqueen and doing insulation that was easy , then helping fixers do the reinforced steel work that was ok , boxing pipes before concrete arrives ,
pump arrives , followed by concrete , wellies on im ready, pushing and pulling concrete , then on poker taking all the air out
63 m3 done and im buggered , then my other pal who is the foreman c,mon rob just got 2 walls to pour then were done about 10m3
slept like a baby that night
thursday same again but this time no pump ,concrete poured into large bucket of 1 of the diggers , then poured were he could reach
,back breaking work another 60m3 poured and ive about had it