Narrowly avoided a disaster this morning. I had spent some considerable time working out the setting out and managed to come to a layout I thought was going to be OK. I had put my batten on the wall and was physicing myself up to start laying the tiles on the wall.....and then the plumber arrived.
He thought we had agreed that the floor would be tiled first and then the wall. He was particularly keen that the shower tray was installed before the walls tiles and the bath as well. He also wasn't convinced the wet wall was sufficiently high enough for the installation frame. If this changes, then the whole setting out would be wrong. Fortunately, he arrived before I had started. Maybe an agreement had been reached but not with me! I guess someone forgot to tell me.
Anyway, after some investigation the wet wall is the right height and my setting out is unaffected by the bath. We just need to work out exactly where the show tray will go. Clearly, I am trying to avoid tiny slithers of tile. So far I am OK but I suspect the shower tray (which comes with an easy plumb kit) is going to screw up the setting out.
He thought we had agreed that the floor would be tiled first and then the wall. He was particularly keen that the shower tray was installed before the walls tiles and the bath as well. He also wasn't convinced the wet wall was sufficiently high enough for the installation frame. If this changes, then the whole setting out would be wrong. Fortunately, he arrived before I had started. Maybe an agreement had been reached but not with me! I guess someone forgot to tell me.
Anyway, after some investigation the wet wall is the right height and my setting out is unaffected by the bath. We just need to work out exactly where the show tray will go. Clearly, I am trying to avoid tiny slithers of tile. So far I am OK but I suspect the shower tray (which comes with an easy plumb kit) is going to screw up the setting out.