H
hmtiling
better chance it's sand cement at that depth. when's the lino forum back btwGood chance it's Anhydrate or simlar
better chance it's sand cement at that depth. when's the lino forum back btwGood chance it's Anhydrate or simlar
You shouldn't force dry s&c screedYeah doesn't mean it couldn't be though.
It's the most commonly used screed these days over UFH And builders as we know don't always follow the rules.
Could just be a fibre reinforced screed but Id want to be sure what I'm dealing with before laying anything.
In answer to the original question With UFH commissioned and running It's possible to dry it out in about two weeks