charlie1

Doing a large job last few weeks 280m2 with70m2 on floor on to original tiles in a wet changing room area that was a bit up and down, water was pooling where it should not have been. &nbsp;Anyway, &nbsp;I was tasked with doing the job and customer insisted they wanted the floor bang on level though out with nice falls in to the wet areas. &nbsp;I done the job using phil Hobson's method of screeding, it took about 50 bags of renovation screed then tiled it. &nbsp;Shop fitters commented when fitting there long spans of sports lockers that the floor was only 2mm out from one end to another. &nbsp; ... Phill you're a legend!!!!&nbsp;<br><br>
 
This thread hasn't been replied to for 14 days, so replying to this one may not get a response. Post a new thread instead.

Reply to Phill Hobson screeding method in the Australia Tiling Forum area at TilersForums.com

There are similar tiling threads here

    • Like
All screed types with wet ufh should commissioned as we know but a sand cement mix screed is...
Replies
16
Views
10K
Just Rizzle
J
S
Hi I am after some advice on the following, I have been to look at a job which had problems in...
Replies
8
Views
8K
shick
S
Hi guys. All the Anhydrite screeds I have done, have UFH (wet) I have always lathered the floor...
Replies
42
Views
13K
R
Good morning I'm after a bit of advise if possible please. Went to see a job, newly built...
Replies
9
Views
3K
rj1884
R
S
Hi Everyone, Am hoping someone can help with some advice here. I have had 120sq mtrs of honed...
Replies
55
Views
23K

Advertisement

Tilers Forums on FB

...
Top