Guys I would like some advise on the 1st supply and fix job I've been able to quote for.
Its an insurance job customer is paying me not insurance company. But he needs the quote to show insurance company.
I've been asked to supply tiles as close to old ones which are 330mm x 330mm trav copy ceramics. So I'm going for Nerea Crema from Tile giant @ £623 for 30m2
I'm charging for all materials as its an insurance job. Is this the norm??
The floors a mess so I shall be leveling it 1st so 11 bags of ultra level form topps included.
To summarise,
27.32m2 leveled and tiled
£1174.39 materials inc tiles
Am I going about this the right way and what would you charge?
Its an insurance job customer is paying me not insurance company. But he needs the quote to show insurance company.
I've been asked to supply tiles as close to old ones which are 330mm x 330mm trav copy ceramics. So I'm going for Nerea Crema from Tile giant @ £623 for 30m2
I'm charging for all materials as its an insurance job. Is this the norm??
The floors a mess so I shall be leveling it 1st so 11 bags of ultra level form topps included.
To summarise,
27.32m2 leveled and tiled
£1174.39 materials inc tiles
Am I going about this the right way and what would you charge?