D
DIY GUY
Hi All.
Quick Introduction, I'm new to this site, but thought I'd join as I'm in desperate need of some advice and guidance! I'm not exactly Mr DIY, but I'm always willing to have a go and really enjoy it when I get my teeth into it. I have a chalet in the French Alps and that's where I'm working at the moment.
I decided to put some underfloor heating down (on top on new insulation boards), which was fine then tiled over the top. However I only laid half the tiles on the first day, but when I tried to continue the next day, the adhesive had dried solid around the edges of tiles I’d put down the previous day. I wasn't able to get new tile up close, I 'unthinking' I got my hammer and chisel and started chipping away! Unfortunately, I nicked the UFH wire before I realised I needed to be extra careful. I had removed the plastic/rubber coat from the wire (2-3mm) and a little bit of silver was showing. I immediately did the Resistance & Insulation test and both were correct as per the start of the job and the manufacture's recommendations. I therefore just taped up the nick/graze in the wire with insulation tape and continued tiling on top.
My questions are really, should I have done that? And will the heating wire burn out at that point in time? If so, is it possible to lift that tile and repair the wire?
Sorry, if the above questions seem a little daft, but I'm gutted that I may have messed this job up after putting in so much work. Any help, guidance or reassurances from you guys will be greatly appreciated!!
Thanks
Quick Introduction, I'm new to this site, but thought I'd join as I'm in desperate need of some advice and guidance! I'm not exactly Mr DIY, but I'm always willing to have a go and really enjoy it when I get my teeth into it. I have a chalet in the French Alps and that's where I'm working at the moment.
I decided to put some underfloor heating down (on top on new insulation boards), which was fine then tiled over the top. However I only laid half the tiles on the first day, but when I tried to continue the next day, the adhesive had dried solid around the edges of tiles I’d put down the previous day. I wasn't able to get new tile up close, I 'unthinking' I got my hammer and chisel and started chipping away! Unfortunately, I nicked the UFH wire before I realised I needed to be extra careful. I had removed the plastic/rubber coat from the wire (2-3mm) and a little bit of silver was showing. I immediately did the Resistance & Insulation test and both were correct as per the start of the job and the manufacture's recommendations. I therefore just taped up the nick/graze in the wire with insulation tape and continued tiling on top.
My questions are really, should I have done that? And will the heating wire burn out at that point in time? If so, is it possible to lift that tile and repair the wire?
Sorry, if the above questions seem a little daft, but I'm gutted that I may have messed this job up after putting in so much work. Any help, guidance or reassurances from you guys will be greatly appreciated!!
Thanks