Just got back from measuring my first 2 jobs.

UK Tiling Forum; Established 2006

Welcome to the UK Tiling Forum by TilersForums.com, built in 2006 by Tilers, run by Tilers.

View all of the UK tiling forum threads, questions and discussions here.

Tilers Forums Official Sponsors

M

monty

Hi peeps

I've just got back from measuring my first 2 jobs....What would you guys charge for these...

1st Job,

En-suite - The walls want tiling from floor to ceiling (300 x 200) in ceramic.He's plastering walls.

1st wall - Has a radiator which he his taking off, and has a window (1m x 1.1m) He's getting trim.
2nd wall - plain
3rd wall - Has sink and boxed in with ply he wants top tiled aswell
4th wall - Door

Total 21 sq. mtrs

The floor wants tiling in 300 x 300 ceramic.. No toilet or sink to tile around.He's plying the floor.

Total 2 sq.mtrs

I've said he can use my trade card to get all materials so this is for labour only.


2nd Job,

Bathroom floor - 3.2 sq.mtrs wants tiling in 300 x 300 ceramics around toilet and sink. Also needs plying onto floorboards (assume 12mm?)

Thanks in advance guys :8:

Monty
 
think your want 15mm if your working to bs for the the ply mate.
id have given a total price including materials even if you give all your trade discount otherwise he may just pick someone who's cheaper.


the floor id charge your day rate plus materials.
 
think your want 15mm if your working to bs for the the ply mate.
id have given a total price including materials even if you give all your trade discount otherwise he may just pick someone who's cheaper.


the floor id charge your day rate plus materials.


He was getting he's own materials anyway so i thought i'd offer him my trade card to give me a better chance of getting the job..

This is my first job so i dont know how long its going to take me..how long would you allow?

Monty
 
it really is a lot easier if the sanitary ware is removed.

1st job 475

2nd job120 this includes plying out

i assume you told him to use 12mm ply screwed at 300mm intervals?


what was your price?
 
it really is a lot easier if the sanitary ware is removed.

1st job 475

2nd job120 this includes plying out

i assume you told him to use 12mm ply screwed at 300mm intervals?


what was your price?

I've said i will ring them tomorrow... i said to the guy 120 for the second job plus mats as he asked how much roughly, So i said that is a rough price until i go back and work it out proper.1st job i was thinking £15 sq.mtr for walls (£315) and day rate for floor (£120) so £435Monty
----
it really is a lot easier if the sanitary ware is removed.

1st job 475

2nd job120 this includes plying out

i assume you told him to use 12mm ply screwed at 300mm intervals?


what was your price?

yes told him 12mm screwed down every 300 mm
 
Last edited by a moderator:
monty why areyou so cheap £15 m2?you should be charging more than that bud.

This is my first job...I'm not sure what to go in at..thats why i'm asking, How much should i be charging?Monty
----
monty why areyou so cheap £15 m2?you should be charging more than that bud.

Your price £475my price £ 435 not a great deal difference
 
Last edited by a moderator:
I've said i will ring them tomorrow... i said to the guy 120 for the second job plus mats as he asked how much roughly, So i said that is a rough price until i go back and work it out proper.1st job i was thinking £15 sq.mtr for walls (£315) and day rate for floor (£120) so £435Monty
----


yes told him 12mm screwed down every 300 mm


hi mate i live in manchester £15.00 m2 thats very cheap for wall tiling i would charge £20.00 & £120.00 for the floor it will take you 1 week to do the walls & floor but if you think the customer wants the cheapest quote then go for £15.00 m2
 
hi mate i live in manchester £15.00 m2 thats very cheap for wall tiling i would charge £20.00 & £120.00 for the floor it will take you 1 week to do the walls & floor but if you think the customer wants the cheapest quote then go for £15.00 m2


Cheers howardWas'nt sure the going rate...might go in at 17.50 as its my first job. How long would it take you?Monty
 
depends mate how long i would take if im busy i would work 12 hours days i would do it in 3 days but if its your first job tell the customer 1 week take your time with it your speed will come later
 

Advertisement

Thread Information

Title
Just got back from measuring my first 2 jobs.
Prefix
N/A
Forum
UK Tiling Forum
Start date
Last reply date
Replies
31

Advertisement

UK Tiling Forum

Thread statistics

Created
monty,
Last reply from
monty,
Replies
31
Views
3,447

Thread statistics

Created
monty,
Last reply from
monty,
Replies
31
Views
3,447

Weekly Email Digest

Back