End of second day on a new bathroom job

1.JPG

2.JPG

3.JPG

4.JPG

5.JPG

6.JPG

7.JPG

8.JPG

9.JPG

10.JPG

10a.JPG

11.JPG

12.JPG

13.JPG

14.JPG
 
It passed my 24hr duct tape test but I have left a heat gun with the owner and I won't be starting walls till Monday so should be done.
Got a massive to do list tomorrow if I want to tile floor Friday:
Drain down and pipe up for new rad and batten out for rad fixings
Reroute cable from old shaver socket to supply new mirror
Overboard floor and set dots and rails (one half of floor slopes down)
Tape and tank
Pour some SLC on my way out
 

Advertisement

Thread Information

Title
Bathroom start to finish
Prefix
N/A
Forum
Bathroom Tiling Advice
Start date
Last reply date
Replies
44
Unsolved
--

Thread Tags

Advertisement

UK Tiling Forum

Thread statistics

Created
macten,
Last reply from
Paul Smith,
Replies
44
Views
13,302

Thread statistics

Created
macten,
Last reply from
Paul Smith,
Replies
44
Views
13,302
Back