Discuss Underfloor heating/issue with builder in the Canada Tile Advice area at TilersForums.com.

Andy Allen

TF
Esteemed
Arms
18,290
1,318
Gloucester
Correct me if I'm wrong but with the loose wire system, don't some manufacturers supply the installer with duct tape to run along the entire length of the cable? Surely this will leave voids and possibly overheat? How is this different?

Mike
It's not duct tape.....it's like the scrim tape plasterer use......at least the last one I did was..
 
These are the other pics

upload_2017-3-9_20-37-57.jpeg


upload_2017-3-9_20-38-25.jpeg


upload_2017-3-9_20-38-59.jpeg


upload_2017-3-9_20-39-22.jpeg
 
O

One Day

Lovely neat work impish question:
Where you have used duct tape to secure the cable in place, can you be 100% sure there are no voids between the cable and the tape? I'm just comparing my masking tape situation to your duct tape and TBH I cant see a difference

Nope. Can't be 100%. But I believe that the cables aren't the weak spots.
Tails and joints are. It's stressed by all manufacturers that those must be embedded.
I always flood my cables (and occasional mats) with slc which is a safer bet than adhesive straight on. Far fewer air pockets - tape or no tape I guess.
 
Nope. Can't be 100%. But I believe that the cables aren't the weak spots.
Tails and joints are. It's stressed by all manufacturers that those must be embedded.
I always flood my cables (and occasional mats) with slc which is a safer bet than adhesive straight on. Far fewer air pockets - tape or no tape I guess.

Agreed I also always use levelling compound which is why I cant seem to get my head around why this has happened
 
D

Dumbo

What was the outcome ?
Main contractor who supplied heat mat paid for repair but asked me to go and replace Tile which I did . But until you have one of these situations you don't realise how critical some aspects of it are . Personally where possible I am going the use the system where the wires push into membrane to limit the amount of tape used like the Variopro system
 

Sean Kelly

TF
Arms
647
1,068
Ruislip
I am thinking that these are the sequence of event:

The UFH has failed.

The customer has contacted the builder.
The builder has contacted the UFH company.
The UFH company has given the builder the number of a person than can seek and repair the damage. If the damage is caused by a faulty cable then the UFH company will bear the cost of the repair.
The repair man has located the problem, removed the tile/tiles and made the repair. The repair man is independent and impartial.

He has identified that the problem is due to the end of the cable getting too hot and the glue has melted on the end cover. The end of the cable must be encased in tile adhesive or SLC. The adhesive and SLC draws away the heat from the cable. If there is a pocket of air around the termination block then the heat generated by the cable is not drawn away quick enough.

The repair man has tested the cable and found that the problem is caused by the installer - sorry.

The repair man gives the bill to the builder.

It seems to me that the builder thought that the problem must be down to a faulty cable but got a shock when he was given the bill (he got the bill because he contacted the UFH company).

In my opinion the builder should have contacted you as you had installed the cable. You would then have rung the UFH company and you would have been given a bill of £360.

The chances are that you would not have found the fault by yourself and you would have had to call in the experts anyway.

The builder has learned a lesson............a lesson that has cost him £360 !!!


You either split the difference with the builder or let this run and run.
 
Hi Sean Kelly

Pretty much spot on although if I was notified in the first instance, I would of gone in with my sparky( have done 2 of these in the past and have been compensated as it was a manufacturing fault ) and if it definitely was below tiles. started with taking up the tile with the cold join beneath it and if it wasn't that joint then move on to the end tail (termination join) At this point if we couldn't get it working, I would have called in the proffessionals and would have paid them to sort it. There are only 2 joints in any one mat, 99% of the time if it fails, it will fail there.
 
Also does anyone know what this means- it was one of the notes on the bottom of the report

Resistance reading less than 999Mohms of heating element to braid (or earth) indicates heating element
insulation damage. Heating cable in working order although low resistance reading may deteriorate and cause future
failure. Fault location not attempted with element to braid (or earth) resistance above 10Mohms due to risk of damage
to heating cable. IEE Wiring Regulations require minimum insulation value of 1Mohm for general supply wiring
 

Reply to Underfloor heating/issue with builder in the Canada Tile Advice area at TilersForums.com

There are similar tiling threads here

    • Like
I have a customer who lives in a 200 year old property. The lounge floor he wants tiled which...
Replies
2
Views
889
Hi All I am after some advice please. We have a retrofit undefloor heating system ( Robbens...
Replies
8
Views
3K
We had a water underfloor heating installed and tiled over. 3 months later we noticed many tiles...
Replies
7
Views
3K
Amethsyt
A
Hi All, I’m ripping out a failed existing tiled floor. Tiles had not been back buttered so...
Replies
3
Views
2K
    • Like
Hi everyone I am building my own house and now I'm ready to tile the floor downstairs. I have...
Replies
1
Views
898

Advertisement

Tilers Forums on FB

...
Top