The biggest mistake here was NOT, heating the floor BEFORE tiling.
even with 6 weeks drying time, his time of year it would not have been dry.
was the screed tested for moisture??
i have made this now to dry our screeds if the boiler can't be commissioned in time for tiling. Can be connected to manifold.


even with 6 weeks drying time, his time of year it would not have been dry.
was the screed tested for moisture??
i have made this now to dry our screeds if the boiler can't be commissioned in time for tiling. Can be connected to manifold.