Discuss I am about to go and dig up my SLC - rebag it and return it to Weber! in the UK Tiling Forum area at TilersForums.com.

C

cornish_crofter

did you check the floor prior to laying the slc??

did you put a straight edge down to see where there was high spotswhere?

or do you just pour and hope for the best......lets know how you went about establishing things

OK this is what I did.

1) Swept floor.

2) Put a level going from the centre of the room out to corners and sides to give me an idea as to where the high spots were.

3) Set a screw in the centre. Judging by where how the level behaved I set this at app 10mm. I knew it would be less in some areas and more in others

4) Drilled, plugged and set screws around the floor app 2 feet apart in a rough grid pattern. Each screw was adjusted to be level with the centre screw or datum screw. I also checked the screws with each other to make sure the heights were consistent. By the time I'd finished I had about 30 odd screws all at the same height as one another. If I couldn't reach a screw with the 6ft level I would take the height of other screws and cross check them. A HELL of a lot of time went into this.

5) Cleaned the floor again, only this time more thoroughly.

6) I then checked again for level screws. As for high spots on the floor, the height of the screws illustrated the high points. So I could see where more SLC would be needed. Also I could see where high spots were and knew that when I poured slc there it would go further so I had to be ready.

7) Primed about 1/2 the floor. I did this so that the SLC would land on it whilst it was still tacky, but not too wet.

8) Mixed the first bag of SLC according to the instructions. As I was working alone I couldn't pour and mix at the same time, so I added about a quarter of the bag at a time. I added 5.25L measured out of clean water. It was at this point I noticed that it was quite runny.

9) equipped with a 6ft derby, plasterers trowel and levels I poured the first mix. Thinking I could settle it at 10mm depth using the screws to guage the depth and the derby to level it I poured it across the far end of the room. It was at this point I found out that this wasn't the case.

10) Phoned Weber and spoke to their product manager and explained that keeping it to 10mm thick was not possible as it was too runny. He advised me to use less water, maybe 4.75l or 5l in the next mix.

11) I then mixed up the 2nd with less water, about 4.75L. I had taken some of the water out of the bucket before mixing. In an effort to get the depth I then poured it on top of the first mix. I suspect this was a mistake. Although I did make an effort to level it out I must have paid too little attention to a corner.

12). As I worked along I mixed up and poured the floor in strips across the width of the room. I varied the water between 5 and 5.25L in an effort to get a feel for the mix. Again I used the derby and the plasterers trowel to level and move it along. I did try to use the derby in the other direction (end away from me as opposed to holing it parallel to the edge of the mix. Where it was slumping too much towards the front I was pushing it back to cover the screws and draw it forwards again. I suspect this created a slight ridge in one area, but I managed to scrape most of it away after a few hours.

13) As I got perpendicular to the door I started working with my back to the door and carried on the same vein. At this area the concrete slab rises a little so I started to mix 5.25L mixes and work back.

14) I only managed to get a couple of mixes in this direction when I ran out. I was hoping that I would be able to work my way out of the door adding the right amount of SLC to sit inside the floor, levelling out as I go, and it would be stopped by the door threashold and walls etc and settle in place.

I didn't spend a huge amount of time trying to get it dead level but I didn't pour and hope for the best either.

Maybe the problem lies in that method.
 
C

cornish_crofter

That's the answer I was looking for.
But to get to 50mm thick you would need to batten out and that I think is where cornish_crofter has come unstuck.
It says on the bag what thickness it will go to but dosn't say how, to get to it.

That is what I understand, and I think you are spot on, as I have said earlier and mentioned to both the tile shop manager and the Weber guy I spoke to today.
 
T

The Legend; Phil Hobson RIP

I have put this method on before, similar to the screw idea. But by using runners set by laser, I find I can get this floor 56m2 accurate to 1mm you could play pool on it:thumbsup:
 

Attachments

  • prep2.jpg
    77.1 KB · Views: 139
  • prep3.jpg
    70.2 KB · Views: 150
  • prep-3.jpg
    77.9 KB · Views: 136
  • prep+2.jpg
    74.4 KB · Views: 144
N

newlineuk

Having used screed for last 25years it's easy for me to say that you could have done it a better way, but what's done is done so, your best option IMO would be to prime and then use a weber product to patch up the low points in patches then skim over the whole floor.
When you've done m2 upon m2 you get the feel of the floor, feeling the low points come natural even with the smallest of trowels.
If I lived closer I would have come over and helped you out. Perhaps one the guys on the forum that do's live locally could help?
 
495
1,118
Somerset
Dear Cornish_Crofter - Nothing is as bad as you sound on this thread. Mistakes and frustration are called "experience."

Experience tells you now that the manufacturers "recommended mixing ratios" are not accurate. Mixing SLC is a bit like mixing adhesive - when you have done it a few times you will get a feel for how "runny" or "thick" you want it to be. Thicker makes it easier to spread accurately, runnier makes it more efficient self levelling. In any event, as a professional, carry spares before you start the job - as someone else suggested if you do not need the extra bags, then you can use them for another job - they have a good 12 month shelf life. I have never found slc that covers the recommended coverage area, but the manufacturers develop their information under laboratory conditions - you are "on site" and that just aint gonna work - again experience is learning how much coverage you get per bag - not what the manufacturer says you will get - how often do you get the recommended coverage from a bag of tile addy?

The SLC you used is very capable of levelling to 10mm in one go. But if it does not go quite right, do a second coat as someone else suggests. If it all goes horribly wrong, remove the hardened slc and start again. Sure you lost some time. Chalk it up to experience.

A tiler I was chatting to last month, same age as me, been in the trade since he left school 30 years ago and has his own tiling company now with 20 employees. He told me that when he started out, laying a screed was a skill all tilers were expected to have. Nowadays too many "trainees" never learn the ancilliary skills that can make your life as a tiler so much easier. All tilers would benefit from plastering skills, screeding skills, and rendering skills - and laying a slc is a part of that. You are having to learn the hard way - losing time and money -whereas the apprentice can make their mistakes at their employers expense - and then only once!

So my honest advice to you is to take several deep breaths, accept the experience you have achieved from this, then get stuck in, and finish the job to a high standard. The next time will be so much easier. Then remember that when those crinkly old sages on here tell us we are going to struggle learning all the skills of a tiler because we have not done an apprenticeship - accept their advice and plan for jobs over running, and paying for our own mistakes.

All the best, and get stuck in again tomorrow. :thumbsup:

Andy
 
C

cornish_crofter

Finished job, 1m x 500mm porcelain, has to be flat for these tiles:thumbsup:

That looks nice there Phil

I think that is what was meant when the Weber guy said it could be done. Unfortunately I spoke to someone else who went and consulted his colleague. If his collegue was thinking about how to get the 10mm in one go that part of the message didn't get to me, although the chap I spoke to reckons he did ask the question about battening it out and the reply is that I didn't have to.

The way I see it I've got 2 options now.

1) Dig around the screws and unscrew them a few turns each to bring them out 3mm above the high point and basically repeat the exercise

2) dig out some channels and put some battons in, levelling out as necessary and do what Phil did. I reckon a bolster chisel or a cutter would do the job..

The 2nd idea is a favourite of mine at the moment. It's more automated and it's the same method I use for rendering walls and screeding floors.

Phil, how do you use a laser to level the battens?. I have a rotating laser level but it won't put a line that far down.

Also, NewlineUK, would you or anyone else care to comment on where I may have gone wrong with the way I did it before please.

Andy, just read your post above. I think I will redo it but I'm not going to take it up. I have spare height on the floor so I'm going to bring it up about 3mm above the highest point and level it to that. I've decided to wait until I have all the material. CTD have given me 2 bags, all their stock at the moment. The Weber rep has basically said he will talk to the product manager about more materials being free issued to me.

What you say about mixing ratios to stiffness makes perfect sense, but again I've said this a number of times, I trusted the manufacturer to give me sound technical advice on this. That is probably my biggest mistake in this instance. Had we had this conversation before I would have bought extra bags and probably battened it out as Phil did his, rather than stiffen up the mix.
 
Last edited by a moderator:
G

Gazzer

That looks nice there Phil

I think that is what was meant when the Weber guy said it could be done. Unfortunately I spoke to someone else who went and consulted his colleague. If his collegue was thinking about how to get the 10mm in one go that part of the message didn't get to me, although the chap I spoke to reckons he did ask the question about battening it out and the reply is that I didn't have to.

The way I see it I've got 2 options now.

1) Dig around the screws and unscrew them a few turns each to bring them out 3mm above the high point and basically repeat the exercise

2) dig out some channels and put some battons in, levelling out as necessary and do what Phil did. I reckon a bolster chisel or a cutter would do the job..

The 2nd idea is a favourite of mine at the moment. It's more automated and it's the same method I use for rendering walls and screeding floors.

Phil, how do you use a laser to level the battens?. I have a rotating laser level but it won't put a line that far down.


Also, NewlineUK, would you or anyone else care to comment on where I may have gone wrong with the way I did it before please.


use a staff !
 
N

newlineuk

That looks nice there Phil

I think that is what was meant when the Weber guy said it could be done. Unfortunately I spoke to someone else who went and consulted his colleague. If his collegue was thinking about how to get the 10mm in one go that part of the message didn't get to me, although the chap I spoke to reckons he did ask the question about battening it out and the reply is that I didn't have to.

The way I see it I've got 2 options now.

1) Dig around the screws and unscrew them a few turns each to bring them out 3mm above the high point and basically repeat the exercise

2) dig out some channels and put some battons in, levelling out as necessary and do what Phil did. I reckon a bolster chisel or a cutter would do the job..

The 2nd idea is a favourite of mine at the moment. It's more automated and it's the same method I use for rendering walls and screeding floors.

Phil, how do you use a laser to level the battens?. I have a rotating laser level but it won't put a line that far down.

Also, NewlineUK, would you or anyone else care to comment on where I may have gone wrong with the way I did it before please.

Andy, just read your post above. I think I will redo it but I'm not going to take it up. I have spare height on the floor so I'm going to bring it up about 3mm above the highest point and level it to that. I've decided to wait until I have all the material. CTD have given me 2 bags, all their stock at the moment. The Weber rep has basically said he will talk to the product manager about more materials being free issued to me.

What you say about mixing ratios to stiffness makes perfect sense, but again I've said this a number of times, I trusted the manufacturer to give me sound technical advice on this. That is probably my biggest mistake in this instance. Had we had this conversation before I would have bought extra bags and probably battened it out as Phil did his, rather than stiffen up the mix.

Difficult to say without being onsite at the time, but the size of the floor area and at that depth without battens to stop spread and not having a great deal of experiance with slc I would have had someone mixing up and two buckets on the go.
Anyone else care to advise?
 

Reply to I am about to go and dig up my SLC - rebag it and return it to Weber! in the UK Tiling Forum area at TilersForums.com

Subscribe to Tilers Forums

There are similar tiling threads here

Hi all, I've laid some Arditex NA over the kitchen floor area (not under cabinets. The area is...
Replies
3
Views
1K
    • Like
TilersForums.com has been online since 2006 and we've had many designs, even three forum...
Replies
1
Views
3K
    • Like
Sometimes work has been hard, sometimes frustrating, stressful etc. But i can't remember the...
2
Replies
18
Views
445
Italy
I
I collected this load directly from weber distribution today in ballyclare about an hours drive...
Replies
10
Views
4K
M
    • Like
Hi all Interested in views from the trade world about how I should deal with a big floor tiling...
2 3 4 5 6 7 8 9
Replies
120
Views
39K

Trending UK Tiling Threads

UK Tiling Forum Popular

Advertisement

Thread Information

Title
I am about to go and dig up my SLC - rebag it and return it to Weber!
Prefix
N/A
Forum
UK Tiling Forum
Start date
Last reply date
Replies
69

Which tile adhesive brand did you use most this year?

  • Palace

  • Kerakoll

  • Ardex

  • Mapei

  • Ultra Tile

  • BAL

  • Wedi

  • Benfer

  • Tilemaster

  • Weber

  • Other (any other brand not listed)

  • Nicobond

  • Norcros


Results are only viewable after voting.

You're browsing the UK Tiling Forum category on TilersForums.com, the tile advice website no matter which country you reside. Our UK based online tiling forum has 48,000 members and started out in 2006.

Top